Page 77 - Impiantistica industriale
P. 77

Focus  Impianti industriali  Focus  Impianti industriali                                            INFORMAZIONE PUBBLICITARIA









                                  FAGIOLI




                                  Installation of a 12,000 ton



                                  pylon foundation












                                  Fagioli was contracted by SBJV, a Danish Joint Ven-
                                  ture led by Itinera, for the transport and installation
                                  of the new Storstrøm bridge which is going to be
                                  built in Denmark between Falster and Masnedo.
                                  This challenging project includes the installation of
                                  foundation plinths weighing up to 2,500 ton, girders
                                  4,000t, pile sections, 250t and plinth 1C, the largest
                                  foundation with a weight of about 12,000 ton.
                                  Fagioli executed the skidded load out operation of a
                                  12,000 ton pylon foundation by means of n.24 skid
                                  shoes each capable of 1000 ton and a semisubmer-
                                  sible barge. The huge concrete block (42 m long, 34
                                  m wide and 22.7 m high), will be the bottom section
                                  of the 106 meter high pylon, which will stand in the
                                  middle of the Danish bridge and carry the suspen-
                                  sion lines for the central girders. Back in May 2020,
                                  work began on casting the huge concrete block,
                                  which has a total of 26 inner chambers, which will
                                  initially be filled with water to place it on the sea-
                                  bed. A temporary steel structure installed (also by
                                  Fagioli onshore team with use of 650t crawler crane
                                  and SPMTs) is set up on the foundation, it has been
                                  design  to  increase  stability  and  guarantee  a  work
                                  platform for the job to come after plinth sinking. The
                                  semisubmersible barge, with 27 ballast tanks, was
                                  equipped with a project specific grillage set. In col-
                                  laboration with barge owner (BOA) the loadout and

                                                                            float off operations developed by Fagioli team suc-
                                                                            ceeded as per plans. The submersion of the barge,
                                                                            to allow the concrete plinth to float, takes place by
                                                                            filling the many ballast tanks in the barge with wa-
                                                                            ter so that it submerge until touching the seabed
                                                                            at 21,5m. Once afloat the block has been towed
                                                                            out to the final position of the plinth itself and mo-
                                                                            ored securely to pre-laid gravity anchors. The pylon
                                                                            foundation was skidded by 24 skid shoes onto the
                                                                            barge BB 34 (140x36x8,5m), an overall operation
                                                                            in a series of critical path phases lasting 5 days in
                                                                            good weather conditions last October.


                                                                                                   www.fagioli.com/it



                                                                                   Impiantistica Italiana - Maggio-Giugno 2022  73 73
   72   73   74   75   76   77   78   79   80   81   82