Fig. 5 – How the barrier works in case of high tide Fig. 9 - Detail of Fagioli gantry lifting system


























Fig. 6 - Malamocco Harbor entrance
















Fig. 10 – Fixed anchor housing
Fig. 7 - Aerial view of “Syncrolift”


composing the MOSE architectural composition.
The overall project performed by Fagioli is divided in
three main steps:
transport and installation of the main sections for the
construction of the “Syncrolift”, an “elevator”
structure which allowed the launching of the
caissons at Malamocco harbor entrance;
building of a specially made catamaran (composed
of two group-owned river barges and dedicated
crosshead beams) to transport and install the
caissons to Bocca di Porto Lido Treporti;
transportation and launching of the first four mobile
gates (other mobile gates will be positioned by
Fig. 8 – Load out of a 600 ton beam by means of SPMTs Fagioli in the next future).