Page 41 - Industrial Plant 2015
P. 41
extremely useful that the supplier has already a result, the process model identification and all other Fig. 3 - Integrated
significant expertise on the process, even more APC related tasks could only be executed in this very architecture
important is a continuous exchange of information with short production run.
the customer in order to design and implement the APC Based on that, the execution team decided to schedule
application. all the most important activities, from data collection to
In this specific case, ABB and the customer created a the identification of the model up to the pre-
very integrated, cohesive and proactive team and with commissioning over a period of about three months,
experience in various disciplines: from Process from August to October 2013.
Technology to Energy Management, from Plant To further add to complexity, integration with the
Automation and Instrumentation to Plant Production existing Plant Automation Systems required interaction
Management. with three, separate, DCS/PLC systems. The execution
ABB and the customer have cooperated in all the team designed and implemented an integrated solution,
project phases: using the OPC DA technology to consolidate the three
• Initial Design; separate automation systems into a single integrated
• Functional Specification issue and review; environment using ABB Symphony Plus platform and
• Base control loop consolidation – instrumentation implemented the APC system on top of Symphony Plus
platform.
and actuator review, PID tuning; All these steps were executed by using Virtual Machines
• Process Model Identification; configured on a customer pre-existing virtualization
• APC System Configuration; server. One of the two Virtual Machines is dedicated to
• APC System Integration with Plant DCS; offline engineering while a second one operates as real-
• Pre-commissioning and test. time control APC. Both Virtual Machines host OptimizeIT
Predict & Control software modules.
Several factors contributed to create a particularly This integrated architecture, presented in the figure 3,
complex and challenging project. Among them, we can allowed the implementation team to reduce lead-time
mention: and avoid new hardware supply to a site that has
• Execution schedule - short and challenging; already dozens of servers and workstations to maintain.
• Integration challenges – Multiple, separate
Benefits
automation systems covering evaporation,
Powerhouse and steam turbines sections. The APC system showed tangible benefits in the
powerhouse management and, more generally, in the
Regarding the project schedule, it is important to notice overall process management, during the tests and the
the normal production run for this type of plant is some pre-commissioning. The main benefits reported can be
3-4 months per year. Sugar beet availability is in fact summarized as:
limited over the year and that influences the duration of • 1-2% reduction of powerhouse average specific
production campaign.
As known from the general technology background, consumption;
plant data collected during normal operation while • 58% decrease in steam venting in the evaporation
performing some small perturbations, the so-called
step tests, are necessary build the APC model. As a section;
Industrial Plants - May 2015
39