systems built on 2 artificial islands (Sarb-North and    conditions of use to prevent cavitation and guarantee        Fig. 3 - Sarb 1 &
Sarb-South) created specifically for the development of  the necessary machine reliability. The delivery of the       Sarb2 artificial islands
this field, as well as on Zirku Island that has been     forty-eight pumps is planned to be completed by mid-
housing for years the treatment of the hydrocarbons      2015.
from other fields. The islands lie at about 120 km from
the Abu Dhabi coast.                                     Conclusion
TMP’s supply consists of forty-eight VS4-type vertical
pumps designed in compliance with the API610             Over the latest years, the leading players of the oil & gas
standards. In spite of the type of pump, usually marked  market have been driven by the search for projects
by high standardization, this project has been           characterised by higher value-added, i.e. by higher
characterized by the high design specificity of the      complexity such as offshore and upstream projects in
individual pumps. Indeed, the end-user’s request to      general. Termomeccanica Pompe has followed this
reduce as much as possible the depth of the tanks led    market trend, implementing a specific investment
to potentially critical use conditions because of the    program (involving engineering, R&D, manufacturing
proximity between NPSH A (Net Positive Suction           and testing facilities) geared towards serving the high
Head) and NPSH R. The development of the pumps           value added oil & gas market segment. Such strategy
had therefore to take into careful consideration these   has borne fruit and allowed the company to confirm its
                                                         prominent role in this demanding market.

Cesare Nardini

After attending the University of Wollongong in Australia  company of Gruppo Industriale Tosoni, which focuses
and Universitat Politecnica de Catalunya of Barcellona     on the railway market. He was first in charge of all
(Spain), Cesare completed his studies in 2000 at           projects related to foreign markets but later moved on
Politecnico di Milano obtaining a graduate degree in       to the domestic market, being also the project manager
Management Engineering.                                    for the engineering and supply of the components for
He started his work experience the same year at Alstom     the ETR 600 / New Pendolino project, developed in
T&D in Montpellier (France), where he worked for two       co-design with Alstom Transport and Giugiaro Design.
years on the development and installation of digital       He finally joined Termomeccanica Pompe’s Project
control system for electrical networks and substation,     Manager team in 2008 with whom he has followed to
starting with product engineering development and          date more than 30 projects in the power generation
then moving on to site- and project-management.            market (including the nuclear sector) and oil & gas
In 2002, he changed to the automotive industry and         market (including both the onshore and offshore
went to work as a project manager for Saira SpA, a         sectors).