Page 62 - Industrial plants
P. 62

projects  the  promoter  finances,  designs,  constructs,   as far as possible on the contractors.  The contractor
                             and operates a facility over a given period but it does   undertakes responsibility for constructing the asset
                             not revert to the government as it would using the   and is expected to build the project on time, within
                             BOOT strategy.                            budget and according to a clear specification and to
                             Further extensions of the concept are BRT or BLT   warrant that the asset will perform its design function.
                             (build, rent/lease and transfer) or simply BT (build and   Typically this is done by way of a lump-sum turnkey
                             transfer immediately, but possibly subject to instalment   contract. 
                             payments of the purchase price). 
                                                                       O for own
                             Another approach, BTO (build, transfer and operate),   The concession from the state provides for the
                             has become increasingly popular in the Far East and   concessionaire to own, or at least possess, the assets
                             is  particularly  preferred  by  power  and  that are to be built and to operate them for a period of
                             telecommunications authorities.  It is a simpler   time: the life of the concession.  The concession
                             transaction or concept than BOT and BOOT that can   agreement between the state and the concessionaire
                             be implemented in a shorter time without the need for   will define the extent to which ownership, and its
                             the formation of a project company and with the   associated attributes of possession and control, of the
                             project assets being owned by the public sector.  assets lies with the concessionaire. 
                              
                                                                       O for Operate
                                                                       An operator is to assume responsibility for maintaining
                             The Components of BOOT                    the facility’s assets and operating them on a basis that
                             B for build                               maximises profit or  minimises cost  on  behalf  of  the
                             This is probably the easiest part of the acronym to   concessionaire and, like the contractor undertaking
                             understand.  The concession will grant the promoter   construction of the project, the operator may provide
                             the right to design construct and finance the project.  A   funds to finance construction and be a shareholder in
                             construction contract will be required between the   the project company.  The operator  is often an
                             promoter and a contractor.  The contract is often   independent company appointed under an arm’s-
                             among the most difficult to negotiate in a BOOT project   length agreement.  However, in some cases the
                             because of the conflict that increasingly arises between   promoter operates  the facility directly through the
                             the promoter, the contractor responsible for building   promoter company. 
                             the facility and those financing its construction. 
                             Banks and other providers of funds will want to be sure   T for Transfers
                             that the commercial terms of the construction contract   This relates to a change in ownership of the assets
                             are reasonable and that the construction risk is placed   which occurs at the end of the concession period,