Page 91 - Industrial Plants
P. 91

flexibility and to minimize the need of further civil   the hydraulic stability of the SPMT trailers during
            works enroute, turntables were used over two   the  transport of  the  stacked  modules  from  the
            independent sets of SPMTs of 48axle lines with   stacking area to their foundations. It must be
            four PPUs in 4-file open compound configuration.  highlighted/It is pivotal/important to highlight that
            Furthermore grounding and installation at site   every module featured unique dimensions and
            proved to be particularly demanding due to the   weights  together  with  a  varying  number  of
            combination of cargo weight, ground conditions,   supporting beams, ranging from three to eight
            limited space at site and the daunting environmental   beams. Even if the modules were of identical size,
            factors of Southern Iraq. Hereby the installation   the beam count differed in span length of the
            and pre-assembly of 99 heavy modules with unit   beams. As a consequence, the transportation
            dimensions up to 47.50 meters of length, 15.00   process necessitated a tailored approach for each
            meters of width and 13.80 meters of height and   stacked module and for each haul from stacking
            weighing up to 672 tons each posed a series of   area to foundation the SPMT axles had to be
            unique challenges, each demanding careful   rearranged accordingly. This dynamic approach
            consideration and strategic planning.     ensured that the trailers were adjusted to support
            The installation of these heavy modules was   the beams of each module accurately.
            divided into two categories. The first and relatively   The installation and stacking procedure began
            simple category comprised of modules which   with lifting the lower modules to above ground
            were to be installed without stacking, while the   level using SPMT trailers. Once elevated to the
            second category consisted of the stacking of   maximum reach of the SPMTs, the modules were
            lower and upper modules in two tiers at the final   carefully positioned onto custom-designed stools.
            installation area, with module pairs reaching   Subsequently, the trailer was lowered and released
            dimensions up to 28.30 meters of height and 821   under the module. Cruciform steelworks were
            tons of weight. These stacking operations required   strategically placed over the trailer and again the
            enormous precision, as the fabrication standards   SPMTs jacked up the modules to their maximum
            of the modules did not allow tilting of more than 2°   elevation. This cycle continued and gradually
            and as the installation only allowed a 30 mm   increased the modules clearance until  sufficient
            tolerance. Furthermore the single installation   space was achieved to assemble their legs.
            positions  of  the  99  heavy  modules  were  to  be
            found in  different locations on  site  with varying   “By leveraging innovative techniques
            distances.  Applying  a  conventional  stacking   and equipment, the construction
            method would have required the employment of a   teams were able to effectively
            heavy duty crawler crane at each of these    overcome the unique challenges
            locations. However, this method would have   posed by the handling of these
            limited drastically  the site construction progress,   components in the unforgiving
            as the crane would have to be relocated each time   conditions of the Iraqi desert
            for  every  single  unit  installation.  Considering  the
            time to dismantle and reassemble the crane for   Subsequently, lifting the upper modules from the
            each lift this traditional method would have   top side with CJ ICM’s 1,600 tons crawler crane at
            consumed too much time and would have had a   the  designated  stacking  area  also  came  with
            negative impact on the project. In order to avoid   different challenges. The upper modules were
            these interruptions given the already demanding   lifted vertically from each lifting eye, differing from
            schedule, engineers from both CJ ICM and JGC   six to 16 lifting points per unit with two lifting eyes
            developed a method using SPMT trailers and   for each supporting beam. A load-spreading lifting
            installing by jacking down the modules from the   frame between the module and the crane’s hook
            trailers directly onto their final foundations. In order   was used. Due to varying dimensions and weights
            to avoid relocating the crane for each lift, it was   of the modules a standard single lifting frame with
            decided to stack the modules in a designated area   fixed dimensions could not have been utilized.
            of the job site and then move the two-tier stacked   This was overcome by building a customized
            modules by SPMT trailers to their respective   lifting frame for this project, which could be
            foundations. Needless to say, distance between   configured prior to each lift by adjusting the length
            the center of gravity of these stacked modules   from 11.40 meters to 47.50 meters and the
            and the trailer increased significantly compared to   frame’s width from 9.00 meters to 15.50 meters.
            moving just the lower or upper module singularly.   This tailor made lifting frame alone weighed 240
            Consequently  one of  the main targets of  the   tons.
            engineers and operators was to carefully maintain   As already mentioned, the modules could not be

                                                                                    IndustrIal Plants - May 2024
                                                                                                                   89
   86   87   88   89   90   91   92   93   94