Page 84 - 62
P. 84

work around the space constraints, S-Oil turned to   mobilized an international crew that worked in double
                             Mammoet to provide a faster lifting solution that would   shifts. They completed the whole process in less than
                             reduce construction downtime. Mammoet responded   7 weeks. Mammoet was on-site and off-site in a record
                             immediately and proposed the PTC 200 DS ring crane   time of 57 days, one month ahead of the original
                             as the best solution for the job. The PTC 200 DS has a   timeline based on the gantry system. This was the first
                             small footprint with a long reach and high capacity for   ever deployment of the PTC 200 DS in South Korea.
                             lifting. As opposed to the gantry system, it could lift all   Mammoet’s approach to use the PTC 200 DS reduced
                             three columns from a single location.     the impact of the works on neighboring areas within
                             Time was also saved in the assembly and disassembly   the refinery and saved a significant amount of time. By
                             of the PTC. It would usually take up to 12 weeks to   cutting 30% off the original timeline, Mammoet was
                             complete  both  activities.  Mammoet  sped  up  and   able to help put the project back on track. Civil works
                                                                       were able to swiftly resume, minimizing the project’s
                                                                       construction downtime and bringing S-OIL closer to
                                                                       opening their new Residue Upgrading Complex.


                                                                       … and off-shore…

                                                                       Providing  more  –  and  more  reliable  – electricity  to
                                                                       Indonesian households is an important step to
                                                                       Indonesia’s growing population future prosperity. Which
                                                                       is why, in 2016, a consortium led by Saipem was
                                                                       commissioned to tap an important gas field off the
                                                                       Indonesian coastline. Essential to this project was a
                                                                       floating production unit: a facility capable of processing,
                                                                       storing and transporting gas to the mainland via
                                                                       underwater pipelines. To save time, the unit, called
                                                                       Jangkrik,  was  built  in two parts –  the  hull  in South
                                                                       Korea and the topside module on the Indonesian island
                                                                       of Karimun. It was the first time anyone had ever
                                                                       attempted to skid and load-out a 14,273 ton module
          Fertilizer vessel installation                               onto a floating production unit hull.
                                                                       Mammoet had engineered and executed complex
                                                                                  skidding projects before, but Jangkrik
                                                                                  was different. To begin with, at over
                                                                                  192 m long and 46 m wide, the
                                                                                  Jangkrik module was massive.
                                                                                  Secondly, early on in the process the
                                                                                  decision was made to construct the
                                                                                  topside on land and skid the integrated
                                                                                  module in its entirely onto the hull. Not
                                                                                  only would constructing the topside on
                                                                                  land save a significant amount of time
                                                                                  in  building  and  testing,  but  it would
                                                                                  also significantly increase the project’s
                                                                                  safety by avoiding the challenges and
                                                                                  risks of connecting and integrating
                                                                                  smaller modules onto the hull at sea.
                                                                                  However, to achieve this required a
                                                                                  close collaboration by all the parts
                                                                                  involved, who needed to adjust the
                                                                                  module’s design and engineering so
                                                                                  that it could eventually be skidded into
                                                                                  place. The hull design needed to be
                                                                                  adjusted as well.
                                                                                  During preparations, construction and
          Ballasting during load-out                                              load-out, nothing was left to chance.


            IndustrIal Plants - May 2018
    80
   79   80   81   82   83   84   85   86   87   88   89