Page 89 - Impiantistica industriale
P. 89

consolidate the Coker Closed Blowdown design
            basis and process configuration, and to develop a
            total investment cost estimate with increased levels
            of accuracy.
            Following the Final Investment Decision, Wood
            has been eventually awarded at the end of 2017
            the  Engineering,  Procurement  and  Construction
            Management Contract, with a completion date by
            the first half of 2019.
            Wood has worked alongside OMV Petrom S.A. in
            the Petrobrazi refinery for more than ten years,
            especially leveraging the experience of the Delayed
            Coker Technology.

            The project activities have been performed
            across several execution centers, which allowed   Figure 5 – Existing Decanter section demolished in June 2018
            connecting the Wood expertise and excellence in
            an effective manner.
            The offices in Milan, Houston and Chennai have
            been involved to deliver the following activities:

            •   The lead office in Milan provided the experience
                in  managing EPC/EPCm  projects  and acted
                as the single point of contact towards the
                OMV Petrom project team
            •   The Houston office provided the expertise on
                the Delayed Coker Technology and developed
                the process design basis
            •   The Chennai office has supported the design
                activities, including the development of the
                3D model  (figure 4) and multi-disciplinary
                deliverables.

            Also a local engineering company has been
            engaged to provide services for compliance to
            the local  codes and regulations,  as well as  the
            Permitting.                               Figure 6 – New Maze system in operation since June 2018
                 The project activities have
                 been performed across several        specific site surveys paid by the engineers from the
                                                      lead office to validate the design solutions studied
            “execution centers (Milan,                remotely.
                 Houston and Chennai), which          Furthermore, with the aim to reduce the total
                 allowed connecting the Wood          investment cost by reducing the extent of the
                 expertise and excellence in an       new interconnecting facilities, the new Closed
                 effective manner                     Blowdown unit has been located within the DCU
                                                      plot area thanks to the demolition of the existing
                                                      Decanter section (figure 5) that has been replaced
            A task force layout, including the full-time presence   by a brand-new Maze system  (figure 6) built
            of the OMV Petrom key project representatives,   adjacent to the Coke Pad.
            has been established in Milan since the early stage
            of the Project to ensure an effective integration of   The construction of the Maze
            the team members across the two organizations.
                                                          system has been completed in
            As the project includes a significant portion of “2018, in the record time of
            brownfield  /  revamping  activities,  such  as  the   seven months from the project
            modification of the existing Coke Drums steel
            structure, piping tie-ins, integration of the control   kick-off date
            and safety systems and upgrade of the existing
            DCU electrical substation, an extensive laser   The  construction  of  the Maze  system  has  been
            scanning survey has been carried out during the   completed in 2018, in the record time of seven
            initial phase of the project, then complemented by   months from the project kick- off date.



                                                                                   Impiantistica Italiana - Maggio-Giugno 2019  87 87