OIL INDUSTRY







                                                                          Through the successful delivery
                                                                          of this project, Wood will
                                                                     “confi rm its strong capability on
                                                                          fast-track execution projects

 ABSTRACT IN ITALIANO                                                     and as a leading provider of
                                                                          services for the Delayed Coking
                                                                          Technology


                                                                      The Subcontracting strategy was based on unit
                                                                      prices contracts that allowed an early award and
                                                                      consequently an early start of the works at site,
 BIOGRAFIA e FOTO DELL’ AUTORE  Figure 7 – View  of the   The Procurement campaign has been oriented   especially with regards to the civil works.
        new  Blowdown  area
        during excavations for civil   to those suppliers being able to combine the   Building the new blowdown unit within the DCU
        works (August 2018)  compliance to the technical specifi cations with   plot area, adjacent to the existing live facilities, the
                            the delivery lead time constraints given by an   excavation works required full consolidation of the
                            aggressive baseline schedule.             slopes by means of sheet piling (12 m deep) along
                            An extensive effort in Expediting and Inspection   the perimeter (fi gure 7).
                            has been required to secure the timely delivery of
                            the goods to the jobsite. A series of inspections   The construction jobsite counted around 500
                            were paid immediately after the orders’ award with   workers during the peak periods in January
                            the objective to freeze the Inspection & Test Plans   and February 2019, leading to overall nearly
                            and to visit the sub-suppliers providing the raw   500,000 direct hours worked without Lost
                            materials.                                Time Incidents.


                           Alessandro Mantovani


                           Alessandro Mantovani, Project Manager, based in Milan, Italy, is the Project Manager appointed for the
                           Coker Closed Blowdown Project.
                           He has a Master Degree in Mechanical Engineering at the Politecnico di Milano (2002). He is a Project
                           Manager with 18 years’ experience in Engineering and Project Delivery, primarily related to the Oil & Gas
                           business. Alessandro has worked on FEED, EP, EPC LSTK, EPCm type projects, in the home offi ce and in
                           the fi eld, within refi ning, power generation, pharmaceutical and mining sectors worldwide. He has hands-
                           on experience in all aspects of the project execution and delivery, managing projects right through from
                           feasibility to start up.



                           Romica Dutu

                           Project Director of Coker Unit Program, OMV Petrom



                 Contratto EPCM per la realizzazione di un nuovo

                 impianto “Coker Closed Blowdown” presso

                 la raffi neria Petrobrazi di OMV Petrom in Romania


                 OMV Petrom ha assegnato a Wood un contratto per la progettazione di dettaglio, la fornitura di materiali e opere,
                 e la supervisione ai lavori di costruzione, per la realizzazione di un nuovo impianto “Closed Blowdown” a servizio
                 dell’unità Delayed Coker, presso la raffi neria Petrobrazi in Romania.
                 Il nuovo impianto, previsto in avviamento nella prima metà del 2019, avrà come obiettivi primari: l’eliminazione
                 delle emissioni in atmosfera durante il normale esercizio dell’unità Delayed Coker; la riduzione delle perdite di
                 prodotto attraverso un sistema di recupero chiuso; il miglioramento dell’effi cienza del sistema di raccolta acque
                 refl ue della raffi neria.
                 Questo progetto prevede una collaborazione sinergica tra diversi uffi ci del gruppo Wood, tra cui l’uffi cio di
                 Houston per la tecnologia in ambito Delayed Coker, l’uffi cio di Chennai per la modellazione 3D e l’uffi cio di Milano
                 per la capacità esecutiva di progetti EPC e l’esperienza del mercato locale e del Cliente.