construction  management  services.  Other  - Less Legal Litigation (Identify issues early and
                             companies are contracted by the Owner directly to   remedy situation before larger problems arise)
                             provide construction services and they are usually   - Owner’s Financing Flexibility
                             managed by the EPCM contractor on the Owner’s   These are just a few of the advantages of EPCM
                             behalf. Think Professional Services contracts, where   style of construction contracting.
                             the project is largely Owner managed and the cost
                             risk and control is weighted towards the Owner.  EPC contracting has it place  in the construction
                             Below is a simplified Chart showing the differences   industry as well. Under certain situations, it makes
                             in the type of contracts and how each would differ   better sense to use this type of construction
                             under the same situations: The list below is not a   contracting than other methods.
                             complete list of differences between EPC and EPCM
                             contracts but it does address many of the major
                             contractual differences. The way each of these  EPC Advantages
                             issues is handled can be modified during contract   - One Stop Shopping “One point of Contact”
                             negotiations to suit the situation and overall goals of   - “Hands off” approach to project
                             the project.                             - Minimal Staffing Requirements
                             EPC and EPCM contracting are both very prevalent   - Minimal Legal Risk
                             types of contracts within the construction industry.   - Best for well-defined projects with Detailed
                             Dependent on the level of risk the Owner of a project   Engineering Complete before EPC Contractor
                             is willing to accept, budget constraints, and the   selected (Minimal Unknowns).
                             Owner’s organization core competencies, will
                             determine which method is best for their project.  “These contract methods can be
                             EPC contracting tends to be more expensive, to the   tailored to the individual projects /
                             Owner, due to the shift of project risk away from the   owner’s needs.
                             Owner and to the EPC Contractor.  On average, a   Each company must decide for
                             project’s cost 10% - 20% more using EPC style of   themselves as to which method of
                             contracting than a project using the EPCM style of   construction contracting is best for
                             contracting. This is due in large part to the project’s   their particular project and situation
                             risk being more evenly distributed between the
                             Owner and contracts / suppliers.         As stated before, these  construction contract
                             Construction contracting trends have been leaning   methods can be tailored to the individual projects /
                             towards the EPCM style of contracting and away   owner’s needs. Some companies can go as far as
                             from EPC contracting for several reasons but both   breaking up each portion of the EPC / EPCM
                             methods have their place in business today.  (Engineering,  Procurement,  Construction  /
                                                                      Construction Management) to separate companies.
                                                                      One company can do the engineering; another can
                             EPCM Advantages                          do the procurement, while still another can do the
                             - Lower Overall Cost                     construction / project management).
                             - Staff’s Sense of Ownership             Each company must decide for themselves, with the
                             - More Control over Process              advice of legal and financial counsels, as to which
                             - Better for less  defined projects with anticipated   method of construction contracting is best for their
                             changes to scope of supply               particular project and situation.



                             Massimo Rebecchi



                             Massimo Rebecchi is graduated in Civil Geotechnical   President and Managing Director he satisfied the
                             Engineering. He he has achieved PhD in Minerals and   Opertions, Project and Quality requirements of
                             Petroleum Engineering in the United States. For   several Main Contractors.
                             years he was freelance professional as Mud Logger   Today Xylem is a Lead Business Consultant Company
                             and Drilling Project Manager. He attended important   in Industrial Construction (Oil, Gas, Process, Mills,
                             construction projects under CCC-Sicon Oil group.  Rail) for Operations, Project Management and
                             As a GE consultant in Nuovo Pignone since 2010, he   Sourcing Quality Management located in Italy,
                             attended several strategic Projects. During this   Emirates, France and Algeria.
                             experience he established Xylem srl in Milan. As

            INDUSTRIAL PLANTS - May 2023