Page 15 - Industrial Plants
P. 15

he existing NPS 24 Trans Mountain   “Frequently affected by snow
                        Pipeline (TMPL) system, built in the   avalanches, making the bottom
                        early 1950s, stretched approximately   inaccessible for most of the year,
                        1,176 kilometres from a storage   geologically and geotechnically  Dry
                        terminal in Edmonton, AB to the   Gulch is unique, due to the contact
            T Westridge          Marine  Terminal  in    between two stratigraphic units,
            Burnaby, BC.                                  resulting in brittle faulting and
            Trans Mountain proposed the Trans Mountain     fracturing of the rock mass
            Expansion Project (TMEP), involving the expansion of
            the existing TMPL system. Spread 5B of TMEP entailed
            constructing approximately 89 kilometres (from KP   Another important aspect is the unknown thickness of
            987+100 to KP 1,076+000) of 914 mm (NPS 36) OD   accumulated talus and depth to the groundwater table
            pipeline. Bonatti, in a joint venture with Kiewit   at  the  bottom  of the gulch.  There  is  unconfirmed
            Corporation, was responsible for pipeline construction   moderate metal leaching and acid rock potential
            activities from KP 987+100 to KP 1,038+100.  associated with the stratigraphic unit to the southwest
                                                     of Dry Gulch. Depending on the chosen crossing
                                                     method, management of rockfall hazard and snow
                                                     avalanches prior to and during construction could have
            Dry Gulch Geomorphological,              required  extensive  temporary  and/or  permanent
            Geological, and Geotechnical             retention measures.
            Setting


            Dry Gulch is a steep V-shaped canyon near the  Construction Schedule
            Coquihalla Summit, approximately 39 kilometres   Restriction & Method Selection
            northeast of Hope, BC. The pipeline route crossed
            the canyon near KP 993+000, about 200 metres   One of the key considerations for the construction of
            northwest of the Dry Gulch bridge on Coquihalla   the crossing was the schedule for completion of the
            Highway 5. The distance between the top of the   works and the available time window. The completion
            northeast wall and the top of the southwest wall is   of the project had been forecasted for the end of 2023,
            approximately 225 metres. The invert of the gulch is   necessitating the completion of the Dry Gulch crossing
            at an elevation of 1,101.3 metres above sea level on   by summer 2023. Additionally, work conditions in this
            the pipeline alignment.                  area were very challenging during the winter season
            The northeast wall of Dry Gulch is about 94 metres   due to low temperatures, snow precipitation, and high
            high, with the upper portion featuring a rock outcrop   avalanche risk.
            with a slope angle of about 57 degrees (locally as
            steep as 78 degrees) and extending for about 45  “One of the key considerations for the
            metres. Further below, there is a blocky rock   construction of the crossing was the
            colluvium lower slope with a slope angle of about 37   schedule for completion of the works
            degrees extending for about 94 metres to the   and the available time window, with
            bottom of the gulch.                      the completion of the project forecast
            The southwest wall of the gulch is 97 metres high,   for the end of 2023
            mostly featuring a rock outcrop with a slope angle of
            about 42 degrees (locally as steep as 58 degrees)   Considering the complex geomorphological, geological,
            and extending about 121 metres downwards. This is   and geotechnical settings and the schedule restrictions,
            followed by a rock block colluvium lower slope with   the feasibility of the crossing, related to the construction
            a slope angle of about 29 degrees and about 32   methodology, was carefully assessed. Initially, “Open
            metres long up to the bottom of the gulch.  Cut” was considered as the default option; however,
            Dry Gulch is frequently affected by snow avalanches,   after a detailed study, it was deemed too complex in
            making the bottom inaccessible for most of the year.   terms of safety, environmental impact, durability, and
            Geologically and geotechnically, Dry Gulch is unique   schedule. After a wide comparison of various
            due to the contact between two stratigraphic units   technologies (HDD, Direct Pipe, Microtunnel, Raise
            (Eagle Gneiss to the northeast and Falls Lake Suite   boring), the TMEP Project Management team identified
            granitic  rocks  to  the  southwest),  resulting  in  brittle   the HDD methodology as the most sustainable option
            faulting and fracturing of the rock mass.  for the crossing execution.



                                                                                    IndustrIal Plants - May 2024
                                                                                                                   13
   10   11   12   13   14   15   16   17   18   19   20