Page 17 - Industrial Plants
P. 17

Figure 3 - Preparation
                                                                                               of Launching Platform
                                                                                               and drilling Pad




























            •   Definition of the optimal distribution of roller   91,000 cubic metres of earthworks overall and 16,000
                supports and the vertical and lateral loads   cubic metres of imported material from adjacent areas.
                required for designing their foundations, under   By Fall 2022, the preparation of foundations and
                pullback and hydrotest conditions;    installation of bridges on Falls Lake Rd. and Falls Lake
            •   Identification of the optimum positioning of the   Creek was completed, and further grading of the drag
                station for the tie-in of two strings, guaranteeing   section was completed in late 2022.
                minimal longitudinal stress and bending moment;  Afterward, stringing and welding of the first two strings
            •   Calculation of any possible longitudinal or vertical   (each  378 metres) was  completed by  the  end  of
                uplift displacement, possibly requiring additional   January, 2023, while fabrication of the main string
                restraints or anchors.                (1,100 metres) was completed in March, 2023.
                                                      A preliminary hydrotest of the strings had been planned
                                                      for April, 2023 – one month before the planned
                                                      pullback – allowing the completion of support
            Pipeline Strings and Rollers Way          installation and equipment mobilization.
            Preparation


            Given the project timeline, Bonatti/Kiewit developed a
            suitable  schedule  to  accommodate  the  required  Pullback Execution
            deadlines, using different teams working in parallel.  The  final  pullback  preparation  activities  started  in   Figure 4 - Secondary
                                                      September, 2023, with the mobilization on-site of the   strings pre-fabrication
            Regarding the proper works of the HDD execution, the
            pilot hole was executed from August to October, 2022
            from the North pad to the South pad, confirming the
            findings of the exploration borehole executed in 2021
            and the low risk of bore collapse along the majority of
            the HDD alignment. Subsequently, the reaming phase
            started in late October, 2022 and progressed through
            the winter.
            In parallel, works for the preparation of the prefabricated
            string and its associated working ROW were carried
            out: initially grading and blasting of the section upslope
            near Falls Lake Road starting June, 2022. Later, the
            section between Falls Lake Road and the Drilling Pad
            required significant earthworks to build a 10 metres
            high  launching  pad  for  the  overbreak  section.  The
            preparation of the pullback ROW required about