Page 18 - Industrial Plants
P. 18

confirmed the loads being consistently within the
                                                                       calculated acceptable limits.



                                                                       Conclusions

                                                                       The Dry Gulch Crossing was a critical activity of the
                                                                       Trans Mountain Expansion Project, and the pipeline
                                                                       pullback  posed  a significant challenge for Bonatti/
                                                                       Kiewit since their involvement in Spread 5B.
                                                                       Considering the exceptional length and project
                                                                       available work space, the engineering, planning, and
                                                                       setting up  of the Dry  Gulch  HDD  pullback  required
                                                                       extraordinary effort and multidisciplinary coordination
                                                                       from late-2021 to mid-2023 to match high safety and
                                                                       quality standards, minimize environmental impact, and
                                                                       optimize the execution schedule. In particular, feasibility
                                                                       studies, detailed design, and construction engineering
                                                                       was developed from Q4-2021 to Q1-2023, including
                                                                       different stages of stress analysis, in static and dynamic
                                                                       conditions, and 3D modelling of the rollers to size the
          Figure 5 - Pullback execution                                equipment required for string management and pipeline
                                                                       anchoring.


                                                                         “Meticulous planning and design
                                                                          allowed the identification of the
                                                                        most reliable and efficient solution
                                                                          for the Dry Gulch HDD pullback,
                                                                       executed safely and smoothly in only
                                                                        52 hours, with eight cranes and 17
                                                                         Bonatti SAFE T-Rex sidebooms - a
                                                                       major accomplishment for TMEP and
                                                                       Bonatti, due to compliance, execution
                                                                       and challenging schedule constraints


                                                                       The engineered pullback required three pipeline
                                                                       strings (1,100 metres, 380 metres, and 380 metres in
                                                                       length),  to  traverse  across  900  metres  of  rollers
          Figures 6 and 7 - Pullback – Falls Lake Road crossing & overbreak section   across rocky terrain with significant horizontal
          detail                                                       direction and  vertical  elevation changes, while
                                                                       crossing two watercourses and one road and being
                             eight cranes and the 17 side booms required for   lifted at about 15 metres elevation for the 200 metres
                             pipeline string management during pullback and the   long over-break section. Meanwhile, other civil works
                             installation of the HDPE buoyancy control pipe inside   required to prepare the rollers were completed in the
                             the NPS 36-inch pipeline strings.         second half of 2022, and the pipeline strings had
                                                                       been welded, hydrotested, and positioned on the
                             The pullback had eventually started on October 18,   rollers from Q1-2023 to Q3-2023.
                             2023, and was smoothly and safely completed in   In conclusion, meticulous planning and design allowed
                             about 52 hours, 30 of which had been required for   the identification of the most reliable and efficient
                             the two tie-ins and with an average pulling rate   solution for the Dry Gulch HDD pullback. The pullback
                             ranging from 80  metres/hour to  120  metres/hour,   was executed safely and smoothly in only 52 hours,
                             exceeding the best estimate scenario. The maximum   with eight cranes and 17 Bonatti SAFE  T-Rex
                             pulling force was within the expected range, and   sidebooms. This was a major accomplishment for
                             also  the  continuous  monitoring  of  the  vertical  and   TMEP and Bonatti due to the compliance, execution
                             lateral loads on the cranes and side booms   and challenging schedule constraints.

            IndustrIal Plants - May 2024
    16
   13   14   15   16   17   18   19   20   21   22   23