yard capabilities on par   Another local designated subcontractor has
                                                                           undergone qualification for insulation coating of the
                                                with Egina Project         linepipes. The contract is now in place to coat either
                                                                           with 3LPP (anti-corrosion) or 5LPP (insulation)
                                                requirements. Next         technology over 90 km of linepipes in Onne facility,
                                                                           near Port Harcourt (figure 8).
                                                after the completion of
                                                                             Saipem has run an extensive training
                                                LBL structure               program for local engineers to develop

                                                fabrication (figure 7),            multidisciplinary expertise

                                                this has enabled EWT       As part of the strategy of building local capacity,
                                                                           growing a proficient and qualified human
                                                to qualify for the         resource base, and transferring know-how,

                                                fabrication of some of

                                                the most massive

Fig. 8 – Coating at PCNL yard at Port Harcourt  structures of the project
Onne area                                       - the mooring piles of

                                                the Oil Loading Terminal

Buoy, which was recently activated.

Project in progress

Egina UFR is progressing well with detailed design
already being three quarter completed. Next in the
EPCI chain, the supply and procurement activity is
soon to reach half way while the fabrication activities
are gearing up, having already progressed to nearly
20% overall by now.
Four main fabrication sites in Nigeria and abroad are
now fully engaged in delivering the 40,000 tons of

                                                                                     Fig. 11 – Coating of line pipes

Fig. 9 – Risers anchoring piles at Saipem’s yard in Port
Harcourt

                                                          Fig. 12 – Coating of line pipes

Fig. 10 – FPSO anchoring piles at Saipem’s yard in Port   assembled steel required to make up the complex
Harcourt                                                  Egina UFR subsea infrastructure.
                                                          Some of the heaviest structures such as risers foun-
                                                          dations anchors (figure 9) and the first batch of
                                                          FPSO anchoring piles (figure 10) are already pro-
                                                          gressed well over halfway which testifies of the pace
                                                          at which this gigantic project is being executed.
                                                          Coating of linepipes in the in-country plant is steam-
                                                          ing ahead with over 45km of 12 and 14 inch linepipes
                                                          already coated to date (figures 11 and 12).