Page 121 - Industrial Plants
P. 121

The importance of E&I equipments



            Revamping in a Scientific research


            Institute






            Costruzioni Elettrotecniche Cear highlights its experience on revampings






                n a scientific research institute a lot of technological   visit pictures and notes
                equipment are installed with high level of performance   related the part of each
                and availability required for their scope of use. Even   power and control system
                if a long lasting term of use is foreseen, usually they   that has to be modified; so
                need maintenance over the years and, sometimes,   that the technician, that
            Iaccording to the new requirements related the   would have been involved
            update of the plant, they need to be modified.  in the project, collected
            This means for the Scientific research institute a big   information regarding a
            investment but also a challenge where should be foreseen   PLC control panel,  SCADA
            a minimum risk of failure or inconvenience related the   system, Motor Control
            above modification or maintenance.       Center and all field existing electrical and instrumentation
            For this reason, teams of engineers and technicians are   connection. This  was necessary  to develop  the  new
            involved in a very tight schedule where everything is   engineering documents, that have to integrate and
            planned in order to avoid any mistake or unforeseen event.  complete the old ones given by the customer, as for
            Costruzioni Elettrotecniche Cear has been involved in the   example the design of the updated equipments and
            past two years in many  projects of revamping for some   technical  documentation  necessary  to  buy  and
            E&I equipments related technological units of an important   manufacture new parts of the control system.
            European Scientific Research Institute.  All of these documents, needed to be checked and
                                                     approved  by  the  customer  and  once  this  activity  was
            The involvement of Cear has started in 2015 for the   completed,  the  design  phase  could  start  in  order to
            Revamping and update of existing Control System of 3   develop the modification of the E&I control System and
            cooling and ventilation group of an important section of   start manufacturing some hardware parts, in our workshop,
            laboratories.                            to be installed during installation phase.
            Each of this cooling and ventilation group control system
            was composed by a Motor Control Center for feeding the   The main hardware modification developed on PLC
            machineries and was composed by a PLC control panel   Control panel for the three control systems was to
            that was communicating with a SCADA through a serial   manufacture a new backplane, that have to substitute the
            communication.                           old one, fitted with all equipment required for the proper
            Cear’s involvement has started with doing a site visit done   handling of the process. The backplanes shall be designed
            at the very beginning in the  bidding stage, in order to   following technical prescriptions related Electrical and
            collect all the relevant information, pictures and datas   process standards issued by the laboratories.
            necessary to be matched with the technical dossier   These backplanes shall be dimensioned for a nominal
            received by the customer.                current of 25 A and a maximum short circuit current of 10
             After this preliminary stage and order awarding, the job   kA (Ik1) with a power supply is 1P+N+PE; they should
            have been done in several stages that where defined by a   have had installed newest models of PN/DP PLC and the
            specific project schedule that foresees that the job has to   I/O  cards and some  additional  cable connection and
            be partially done in factory and partially done with   feeders necessary for the modification of the control
            installation and modification on site .   system, as for example temperature switch for ventilation
                                                     system or flow switches for each pump to digital PLC
            The importance of site survey            inputs;  all  of  these  requirements  where  related  to the
            At a first step was very important to collect during the site   upgrade of the new control systems.