Page 122 - Industrial Plants
P. 122

The customer , after
            The activities on fi eld                  completion of this activity
            The installation phase have been very intensive and has   required  also  Cear’s
            considered  the  following  activities  for  each  of  the  three   technician presence for
            sections of the cooling and ventilation system:  pre-commissioning  and
            •  The modification of the cubicles: related the PLC   assistance during the
               control panel, MCC cubicles and PC SCADA cubicles,   overall commissioning of
               in order to re-adapt the system to new requirements  the system to execute the
            •  The removal and installation of new backplanes for PLC   I/O tests on the equipment
               control panel, with all related cable connections  that has not been replaced
            •  Cabling, including supply and installation of new   and  the new  equipment
               cables; the main requirement was about the removal of   installed.
               the existing communication cable to the Trane UPCM
               PLC  located  in  the  control  cubicle  and  Pulling  an   A final completion of technical documents, after the latest
               Ethernet cable between the Ethernet switch installed in   commissioning activity have been produced in order to
               the control cubicle and the main Ethernet socket   give updated documents with the last modification done
               installed in the PC cubicle.          on field during final stage, with the delivery of the so called
            •  In addition it was very important to do a checking of all   “as build” drawings.
               electrical and instrumental connection for the feeding
               and feedback of instruments on field and  their
               interconnection with the PLC cubicles. Finally, this  Conclusion
               activity required to do a complete survey of cabling and   To resume, Cear for this revamping project have done the
               connections of the existing installation, with integration   following main activities, in time, following the strict
               of the acquired information in the electrical drawings.   schedule submitted by customer :
            •  Supply and electrical and mechanical installation of   •   Engineering document modification
               additional instruments. Each section of the cooling and   •   Supply of The control system including PLC, I/O
               ventilation system had different needs regarding   modules and Power Supply;
               instrumentation, but the main instruments provided   •   Modification  of  the  control  cubicle  including  the
               and installed with all the electrical interconnections   supply of new equipped backplanes;
               were:                                 •   Modification of the field cabling including supply and
               -  temperature sensors, that were replacing the oldest   installation of new cables;
                 one that were no more compatible with new   •   Supply  and  installation  of  new  process
                 technologies,                           instrumentation;
               -  additional flow meters to be connected to the   •   Pre-commissioning and commissioning activities
                 existing circuit,                   •   Supply of as-built electrical drawings
               -  differential pressure transmittal to be connected to
                 the existing circuit,               Nowadays revamping projects are becoming even more
               -  water counter, on the filling circuit following the   important type of jobs required by customers, in order to
                 modification of the pipeline        save money and in some case to update technological
            •  Installation of missing ID labels on the existing   systems that need to give better performances. The
               installation, as per new requirement  opportunity to express Cear capabilities for a research
            •  Test and commissioning: the completion of activities on   institute, that has very strict protocol of quality procedure,
               site foresee that this new section of plant have to be   is a successful result of our activity also in this field,
               tested following a specific procedure with a dedicated   where  old  and  new  equipment  need  to  be  matched
               test report to be issued.             together.




                                 Alessandra Ranno


                                 Alessandra has studied Languages and Communication,   in charge as Sales and Marketing Manager for
                                 then graduated in Marketing & Communication at the   coordinating  marketing  activities,  sales team  and
                                 University of Milan. She’s in Cear since 2010 and she’s   implement international markets.





            INDUSTRIAL PLANTS - May 2017
    120
   117   118   119   120   121   122   123   124   125   126   127