Page 84 - 60
P. 84

Table 1 – The most significant key parameters of the polypropylene (PP) and high-density
       polyethylene (HDPE) plants

        Seq.   Description                     PP        HDPE
        1      Concrete Foundations[m ]        23,350    9,400
                              3
                                                                      Moreover, notwithstanding the fact that initially local
        2      Cast in situ RC & buildings (m )  11,900  10,000       vendors were not ready to satisfy the expectations
                                  3
                                                                      of an international EPC contractor, MET – through
        3      Steel structure (ton)           5,000     4,000        its hub KTAZE – invested efforts in driving the stra-
        4      Equipment (n.)                  500       400          tegic local suppliers to fulfill its needs project-wise
                                                                      and to become more effective in providing mate-
        5      Piping prefabrication (dia)     73,600    59,000       rials/services  with  the  quality  requested.  In  addi-
        6      Piping erection (dia)           149,000   66,000       tion, managing a main subcontractor which was
                                                                      responsible of all construction and commissioning
        7      Electrical cables (m)           466,000   321,000      phases of the project implementation was naturally
                                                                      one of the most important aspects, together with
        8      Instruments main cable laying (m)  363,500  355,000
                                                                      the necessity to find locally skilled and technically
        9      Instruments installation (n.)   5,000     3,000        prepared resources, as blue and white collars are
                                                                      still in the learning curve to master how to deal with
                                                                      international contractors. In this respect, all local
                                                                      resources involved in the projects were successful-
                            Challenges, but also opportunities        ly managed, educated and mentored in term of
                            Since the beginning, the execution of these two   safety issues.
                            plants in Azerbaijan seemed to be challenging, due
                            to  several  different  conditions  which  affected  the
                            normal scheme of the implementation of a project  The execution
                            of this kind. Naturally, challenges bring always op-  Since the inception of project activities, engineering
                            portunities and MET has been able to leverage   was implemented in order to deliver the necessary
                            them to strengthen its position in the Country and   documentation to obtain all the permitting, without
                            in the relevant market.                   which site construction activities would not have
                            The main challenges were the implementation of   started.
                            a relative big project in a Country where no in-  The  preparation  of  the  document  “Issued  for
                            vestments of this type were performed in the last   Permitting” has been coordinated with a Local
                            forty years, and ensuring on a fast track basis the   Design Institute in which a dedicated team of
                            coordination with Azerbaijani authorities for permit-  specialist was deployed. The decision to deploy
                            ting matters and technical standards to be utilized   such team and to assign an Interface Manager
                            in  the design phase of  the  project.  Furthermore,   fully dedicated to the administration of local
                            since activities were carried out in several opera-  technical authorities were among the success
                            ting centers located in different areas of the world   factors in the arrangement of the permitting,
                            and thus different time zones, the development of a   allowing a coordinated and structured informa-
                            concrete and effective time management strategy   tion flow decreasing significantly the timing of
                            was required to have the project team working in   the permit issuance. All permitting documenta-
                            complete coordination, leveraging I&CT tools and   tion duly signed by all necessary local autho-
                            efficient integration of the teams.       rities were obtained on-time and in-line with
                                                                      project and Client expectation. As a matter of
                                                                      fact,  construction  sequences,  timely  availabili-
                                                                      ty of permits and materials are jointly of great
                                                                      importance to implement a project of this type
                                                                      In this scenario, the Group managed to provide fe-
                                                                      asible look-ahead work-fronts for the construction
                                                                      subcontractor which were also supported by the
                                                                      concrete utilization of 3D model tools.
                                                                      The utilization of another Group tool such as Ma-
                                                                      rian allowed a full control over the in-coming ma-
                                                                      terial at the warehouse, thus introducing a level of
                                                                      insurance of the implementation of different work-
                                                                      fronts, which was vital during the first phase of the
                                                                      construction project.


                                                                      Sophisticated Coordination with Client and PMC
                                                                      It has been implemented a sophisticated day-by-
                                                                      day coordination scheme with Client and its PMC
                                                                      in order to achieve the following targets:
                                                                      •   full transparency and trustiness in project ma-
                                                                         nagement;



       82  Impiantistica Italiana - Gennaio- Febbraio 2018