                                                                      gning and engineering activities become more
                             For more detailed information about      linear and it should be easier (and faster) to get
                             IOGP and JIP33, refer                    approvals.
                                                                       There are also likely to be fewer last-minute chan-
                             to the following links:                  ges and inspection hold points.

                             Find out more about IOGP and JIP33:
                             IOGP                                     The Process
                             JIP33 - About us                         JIP33 has gone through Phase 1, the “Pilot” pro-
                                                                      gram. Fifteen oil companies got together and set
                             IOGP Members:                            out specifi cations. Four equipment standards were
                             https://www.iogp.org/members/            developed to prove the concept.
                                                                      After the verifi cation of the saving in cost and time
                             Committees:                              of coming from the standardized specifi cations,
                             https://www.iogp.org/our-committees/     the project moved to Phase 2 during the 2018,
                                                                      where further procurement specifi cations where
                             To feedback on JIP33 specifications:     created.

                             https://www.iogp-jip33.org/library/
                             https://www.iogp-jip33.org/getinvolved/  During Phase 1 and 2, 14 sets of specifi cations
                                                                      were published.
                                                                      Phase 3  started in 2021 and almost 40 specifi -
                                                                      cations have been published with more planned.
                            quickly - saving time, resources, and cost.
                            Because requirements are standardized, in ad-  All the details can be found in JIP33 web site.  All
                            dition to the increased quality, suppliers can also   specifi cations are free and available to download to
                            focus more on continuous improvement and more   anyone. As each specifi cation is drafted, it will be
                            innovative designs.                       posted online on the specifi cations development
                            Consistent requirements also  mean  that desi-  page for comments.








                            Dario Lo Monaco


                            Dario Lo Monaco  has a degree in Mechanical Engineering from University of Brescia.
                            Starting from Engineering and Construction company of small-scale Cogeneration Plants, he joined
                            Saipem (former Snamprogetti) as Rotating Equipment Engineer dealing with Turbomachinery.  He ex-
                            perienced different responsibilities such as Engineering, Interface Management, Field Engineering and
                            Construction Supervision, Project Technical Management and Proposals, both in Onshore and Offshore
                            Projects. In Saipem he is currently Head of Procurement for E&C Onshore Division Milan Hub.
                            He is currently the Focal Point for IOGP JIP33 in Saipem as EPC Partner.





                             Giorgio Bonasio


                             Giorgio Bonasio  has a degree in Chemical Engineering from the Milan Polytechnic. He started  his work
                             experience in Snamprogetti, fi rstly  in the  instrumentation and process control activities .
                             Later he took care of the process packages. During his activity , he participated in the engineering phases
                             , as well as in the construction and start-up of oil and petrochemical plants.
                             In Saipem  he  currently operates in  the category  commodity management  for package and furnace.
                             He is also involved, in Saipem organization, in JIP33 initiative.