was performed by Push Up Units (4 Electronically   ity in handling the different configurations of the   Pict. 5 - 6
            Synchronized Lifting Towers with 2,400 ton   jacket modules which were provided with steel
            capacity), that were a fully synchronized lifting   stoppers  positioned  at  9m  above  the  ground
            system, allowing to lift entire Jackets without any   (Picture 7).
            risk of overloading. For each step modular barrels   SPMTs took the load with the frame structure
            were inserted, elevating or lowering down Jacket   and lifted the jackets. The steel stoppers were
            by 1 m for each step (Pictures 5 and 6). Due to   welded in order to support the load of the jacket
            their extreme maneuverability, SPMTs can be used   during the lifting and transport operations. The
            in very congested areas, such as fabrication yards,   SPMTs convoy was positioned under the jacket
            with ground Bearing Pressure not exceeding 10t/  modules in about 30 minutes. Fagioli after
            m .                                       executing the weighing operations by means of
              2
            This engineering excellence allowed Fagioli to   load cells, moved the jackets from manufacturing
            seamlessly deliver and subsequently load out   area to the storage area, using the frame system
            the jackets onto the deck of a specialist shipping   explained above. Once at the storage area the
            vessel for the final journey.             jackets were provided with an upper grillage for
                                                      the sea transport activity by barge. After this
            Heavy transport                           operation a 128 m barge was waiting for the load
                                                      out of No. 4 jackets.
            activity in Spain
                                                      In 2021 and 2022 Fagioli was contracted for the
            Fagioli was contracted by Navantia for the tran-  transport and load out operations of further no.   Pict. 7
            sport and load out operations of Offshore Wind
            Farm Jackets in Spain for a total of no.104 items
            between 2017 and 2022. The jackets, weighing
            between 950 and 1,200 ton, were handling by
            Fagioli with other dedicated and tailor-made
            structures for the load out operations onto bar-
            ges.
            For  the  first  project  back  in  2017  the  main
            challenges were:
            - How to speed up the load out operations in
            a safety manner, considering the dimensions
            and weight of the jacket modules and the fact
            that barge voyages were planned for the sea
            transport
            -  How  to  avoid  delays  due  to  wind  and  bad
            weather conditions
            - How to handle execute the load out activity
            onto a barge, able to take the load of No. 4 ja-
            ckets positioned in a row. Also for this project
            Fagioli came up with the idea to build a tailor
            made frame structure (different from the Indone-
            sian project) to answer to the above questions.
            Fagioli found the solution with a retractable edge
            main beams with movable stoppers. This solu-
            tion was the winner one: it allowed the flexibil-