The outstanding growth of these
                 markets allows Fagioli to put on
            “the table all its advanced
                 technological know-how,
                 experience and state-of-the-art
                 equipment, to become a reliable
                 partner for the engineering,
                 heavy transport and lifting
                 activity for the Renewable
                 sector, with a specialization
                 in Offshore Wind Energy
                 extra-heavy items handling
                 operations



            Fagioli was contracted for the weighing, transport
            and load out operations of Wind Offshore Jackets
            in Indonesia (Picture 2) and Spain.


            Indonesia Project
            Fagioli PT Fagioli Indonesia was awarded the
            contract for two projects based in Karimun
            Indonesia by our business partners PT Saipem
            Indonesia,  for  the  execution  of  all yard service
            activities concerning a total number of 88 Jackets   was completed each of the structural jacket legs   Pict. 1
            for the Wind Offshore Renewable industry.   was fitted with purpose made lifting clamps in
            The service provided  by Fagioli covered and   preparation for the vertical transport.
            included the following services:          Once  successfully  upended  the  jackets  were
            Site  activity  such  as  jacket  horizontal  transporta-  next fitted with a prefabricated Transitional  piece
            tion, jacket upending, TP installation, jacket vertical   weighing a further 350 tons. The TP was located by
            transportation, and Loadout by Ro-Ro onto dedi-  means of male/female location sockets and then
            cated heavy lift ships of 32 four-legged 1,653 ton   welded into osition and lifted using a Specialized
            windfarm jackets with Transition Piece on top for   TP lifting tool assigned to the  project after a
            the first project , and 52 three-legged 1,427 ton   careful structural integrity check made by Fagioli
            windfarm jackets with Transition Piece on top, and   engineering department with the support of the TP
            2 three-legged 1,779 ton substation jackets.  lifting tool provider (Picture 3).
                                                      Once these works were completed the entire struc-
            The transport of items from the point of fabrication,   ture now weighing over 1,700 tons was moved
            to the upending area, whilst in the still horizontal   vertically by a 96 axles SPMT convoy fitted with a
            position was achieved by using different   2 specially fabricated Fagioli transport beams that    Pict. 3
            configurations of total 72 axle lines of SPMT, 4 in
            house designed and fabricated connecting beams
            and 4 Power Pack Unit, all fitted with specialized
            purpose build jacket saddles fitted to the decks.
            These were positioned at each end of the jacket
            structure.
            Once at the upending area, a tandem lift operation
            was  executed  to  lift  the  jacket from the  deck  of
            the SPMTs, once suspended the SPMTs were
            removed and the jackets were lifted straight into
            the vertical position before being set back down on
            purpose made jacket stands at the base of each
            leg (Picture 1). For these highly specialized lifting
            operations Fagioli used the Liebherr LR13000 that
            has a maximum lifting capacity of 3000 tons, unit