Figure 2 – IPMA and Contract
Models scheme
The IPMA consists of a very simple and basic con- This operating model is very effective and fast. Mo-
tract and a number of attachments that cover all reover can be used by different project departments
possible cases. A workflow scheme is represented involved in separate phases and at different times:
in Figure 2. usually the FEL1 and FEL2 steps are managed by
A call-off mechanism and assignment is set out in the Technical Development department of OMV
the IPMA: if OMV Petrom desires to have Amec Petrom, while FEL3, EXECUTE and Supply & Wor-
Foster Wheeler to perform services, OMV Petrom ks contracts are assigned to the OMV Petrom
issues a Request for Proposal (RFP) to Amec Fo- Project Management team. Therefore, the split into
ster Wheeler in accordance with the procedure three contract models as highlighted in Figure 2 is
included in the attachments and using a specific self-explanatory and its successful application over
template. By submitting its proposal, Amec Foster the last two years has proved the need to establish
Wheeler includes an Assigned Service Contract such frame agreement.
(ASC) prepared in accordance with agreed proce-
dures and conditions and when it is approved by
OMV Petrom, the ASC is concluded.
The newly implemented operating model
‘Integrated Project Management and
EPCm Services Alliance Agreement (IPMA)
contract’, based on a call-off mechanism,
was very effective and fast
As a matter of fact, the effectiveness of the IPMA is
considerable if compared to the number of projects
awarded since it came into force in 2015 and the
early involvement in the first phases of the projects
is leading to a continuous and successful progres-
sion into the subsequent phases.
It is worth saying that at the end of each phase,
OMV Petrom performs Independent Gate Review
sessions to provide confidence for the Project Ow-
ner and stakeholders that the project requirements
are being met. They also authorize the funding of
the next phase. For the most important projects an
Independent Project Analysis (IPA) is also required
for the evaluation of the phases and whose review
and ranking in relation to industrial benchmarking
supports and reinforces the OMV Petrom Super-