Page 101 - Industrial Plants
P. 101

Sviluppo Economico – MISE” dated January 20, 2015,
                                                     in order to be entitled and allowed to export to Russian
                                                     Federation the equipment inherent the Project.
                                                     In April 2017, APS has met once again all expectations
                                                     bringing thus to fulfillment its mission. Modules,
                                                     equipment and machinery have been modularized at
                                                     the maximum possible level in order to save time and to
                                                     reduce field labour during assemblage and installation
                                                     in the construction area.
                                                     The Modules left the manufacturer’s factory nearly
                                                     complete and certified TR CU (Technical Regulation
                                                     Custom Union), with most of its support structure, pipe,
                                                     instrument stands, electrical wiring, grating, insulation
                                                     and other components built-in and ready for operation,
                                                     once connection is made to the plant’s systems. The
                                                     modules were transported to their final assembly site
                                                     into easily portable skids.
                                                     The main factors that contributed to the success of this
                                                     project  have  been the  APS  local presence in  the
                                                     Russian Federation with its Representative Office in
                                                     Moscow, and the technical support of the State Unitary
                                                     Enterprise GUP INKHP RB, for the examination of
                                                     project and working documentation, including its
                                                     conformity to the requirements of the Russian
                                                     Federation standards. These local partners allowed
                                                     APS to overcome a number of objective difficulties
                                                     related to geographical distance, different institutional
                                                     standards and language.
                                                                                               Fig. 2 –3D Modeling
                                                                                               Project
                n the last few years APS SpA, the Italian
                Engineering and Design Global Contractor, signed
                a contract with a Company, which operates as a
                subsidiary of  ROSNEFT  Oil  Company,  for
                designing, production and supply of diesel
            Ihydrotreating block-module unit. Project
            investment was part of the Client’s business targets to
            satisfy market needs for petroleum products through
            the development of advanced technologies with a
            special attention given to increase operational efficiency
            and modernization, in compliance with Russian
            Regulations. Tarasovskoye field  (Yamal-Nenets
            Autonomous Region, the Russian Federation) was
            chosen as the location of the unit plant and considering
            also the harsh ambient conditions, the plant needed to
            be designed as a block modular supply to reduce
            drastically the installation complexity and time.
            The decision of the Client to rely on APS was motivated
            by the Company’s functional and technical skills in this
            sector, as well as the flexibility and the high expertise in  Project highlights
            Lump  Sum  Turn  Key plants design and  building.  In   The Diesel Hydrotreating Unit, based on American
            order to perform the Contract, since APS operates in   License, has a capacity of 15 m3 / h (2264 barrels /
            compliance with the regulations and laws, including   day); its aim is to reduce the amount of sulfur present in
            those which govern the import and export operations,   the gasoil within the limits defined by the Russian
            APS has obtained the mandatory Authorization from   Technical Regulation approved on 27 February 2008.
            the Italian Public Authority named “Ministero dello   Placement of this modularized plant is planned at the