globAl orgAnizATion
Picture 9 - Connecting
the Acid Gas Absorber to
Fagioli tower lift system
Picture 10 - Detail of the
Acid Gas Absorber and
tower lift system
multilingual people, the most important priority to be completed, approved and made readily
was ensuring that all personnel understood the available on site, this included the following.
importance of safety and followed the same on site
Considering that the team consisted of
multinational and multilingual people, the most Route Survey
important priorities was ensuring that all personnel Detailed survey of the routes to be followed was
understood the importance of safety and followed undertaken. Any clashes/obstructions to be
the same on site. Tool Box talk discussions were removed and modifications to be made were
translated to local languages as well so that documented in the report. After approval of the
everyone involved in the operation were aware of report from the client, the site team would perform
their roles and responsibilities. Such culture drove route surveys at regular intervals to make sure that
performances of the team and zero incidents were the modifications and the improvements requested
recorded with the team receiving recognition from had been completed.
CSTS and BP.
Manuals and Procedures
Engineering Detailed procedures of the operation i.e. SPMT
Considering the total number of modules and Transport Procedure, Crane Lifting procedure,
packages to be transported, a dedicated team Operation procedure, etc., with the permissible
of engineers from Fagioli’s Asia office supported weather conditions were well documented. These
the site Engineering team. To proceed with any protocols were followed rigorously for every
operation a set of engineering documents had operation on site. In the case of any change
46 46 Impiantistica Italiana - Settembre-Ottobre 2019