globAl orgAnizATion






































       Picture 9 - Connecting
       the Acid Gas Absorber to
       Fagioli tower lift system
















       Picture 10 - Detail of the
       Acid Gas Absorber and
       tower lift system
                            multilingual  people,  the most  important  priority   to  be  completed,  approved  and  made  readily
                            was  ensuring  that  all  personnel  understood  the   available on site, this included the following.
                            importance of safety and followed the same on site
                            Considering  that  the  team  consisted  of
                            multinational  and  multilingual  people,  the  most  Route Survey
                            important priorities was ensuring that all personnel   Detailed survey of the routes to be followed was
                            understood the importance of safety and followed   undertaken.   Any  clashes/obstructions  to  be
                            the same on site. Tool Box talk discussions were   removed and modifications to be made were
                            translated to local languages as well so that   documented in the report. After approval of the
                            everyone involved in the operation were aware of   report from the client, the site team would perform
                            their roles and responsibilities. Such culture drove   route surveys at regular intervals to make sure that
                            performances of the team and zero incidents were   the modifications and the improvements requested
                            recorded with the team receiving recognition from   had been completed.
                            CSTS and BP.
                                                                      Manuals and Procedures
                            Engineering                               Detailed procedures of the operation i.e. SPMT
                            Considering the total number of modules and   Transport  Procedure,  Crane  Lifting  procedure,
                            packages  to  be  transported,  a  dedicated  team   Operation procedure, etc., with the permissible
                            of  engineers  from  Fagioli’s  Asia  office  supported   weather conditions were well documented. These
                            the site Engineering team. To proceed with any   protocols were followed rigorously for every
                            operation a set of engineering documents had   operation  on site. In the  case of any change