Page 47 - Impiantistica Italiana
P. 47
of the project. Total of No. 6 cranes are dedicated
to this project by Fagioli, which are the LR11350,
KOBELCO SL6000 and CKS 3000, along with
3 nos. Tadano GR80EX RT Cranes which were
used as support cranes. For the installation of the
heaviest items Fagioli is using its famous tower
lift and stand jacking system, being proprietary of
one of the biggest fleet in the world, synonymous
with safety and high capacity hoisting potentiality
(Picture 7). Fagioli Tower Lift system consisting of
4 nos 600 T strand jack system was also mobilized
and was dedicated for installation of the Acid Gas
Absorber, which was the heaviest equipment to be
installed, weighing up to 1.100T. Fagioli used a 66 m
high tower lift system to execute the operation. The
vessel with a length of about 53,5 m, was moved
into installation area by means of Fagioli SPMTs
: No. 76 axle lines ; three rows made of coupled
trailers (Picture 8) . Once in position the vessel was
hooked to Fagioli tower lift system provided on top
with No. 4 x 600 ton capacity strand jacks (Pictures
9 - 10) . An LR-11350 crawler crane, provided by
our partner for this project (GTA), was used as
tailing system. While Fagioli strand jacking system
was lifting the vessel, the crawler crane, used as Picture 7 - Fagioli tower lift and strand jacking system
tailing was moving ahead in order to compensate
the height of the absorber (Pictures 11 – 12). After
the lifting operation, the acid gas absorber was
rotated about 10.5 degrees and gently lowered personnel followed the schedule incorporating
onto foundations (Pictures 13 – 14). Before the and documenting changes depending on site
actual lifting operations Fagioli executed a tower conditions.
lift load test up to 1,300 ton capacity. Total of 76 The site being located in a highly seismic area and
SPMT Axles were used specifically for transport of experiences rain most months of the year keeps
this equipment. the area wet most of the time. Fagioli’s team leader
and along with HSE personnel were vigilant about
Planning and Safety those unique site conditions and made it a priority
to ensure that workers stayed safe and took regular
The core team of Fagioli Asia laid down a plan breaks in designated shelter areas.
documented in with a detailed schedule. Site “As the team consisted of multinational and
Picture 8 - Detail of the Acid
Gas Absorber before the
lifting operation
Impiantistica Italiana - Settembre-Ottobre 2019 45 45