Page 47 - Impiantistica Italiana
P. 47

of the project. Total of No. 6 cranes are dedicated
            to this project by Fagioli, which are the LR11350,
            KOBELCO SL6000 and CKS 3000, along with
            3 nos. Tadano GR80EX RT Cranes which were
            used as support cranes.  For the installation of the
            heaviest items Fagioli is using its famous tower
            lift and stand jacking system, being proprietary of
            one of the biggest fleet in the world, synonymous
            with safety and high capacity hoisting potentiality
            (Picture 7). Fagioli Tower Lift system consisting of
            4 nos 600 T strand jack system was also mobilized
            and was dedicated for installation of the Acid Gas
            Absorber, which was the heaviest equipment to be
            installed, weighing up to 1.100T. Fagioli used a 66 m
            high tower lift system to execute the operation. The
            vessel with a length of about 53,5 m, was moved
            into installation area by means of Fagioli SPMTs
            : No. 76 axle lines ; three rows made of coupled
            trailers (Picture 8) . Once in position the vessel was
            hooked to Fagioli tower lift system provided on top
            with No. 4 x 600 ton capacity strand jacks (Pictures
            9 - 10) . An LR-11350 crawler crane, provided by
            our partner for this project (GTA), was used as
            tailing system. While Fagioli strand jacking system
            was lifting the vessel, the crawler crane, used as   Picture 7 - Fagioli tower lift and strand jacking system
            tailing was moving ahead in order to compensate
            the height of the absorber (Pictures 11 – 12). After
            the lifting operation, the acid gas absorber was
            rotated about 10.5 degrees and gently lowered   personnel followed the schedule incorporating
            onto foundations (Pictures 13 – 14). Before the   and documenting changes depending on site
            actual lifting operations Fagioli executed a tower   conditions.
            lift load test up to 1,300 ton capacity. Total of 76   The site being located in a highly seismic area and
            SPMT Axles were used specifically for transport of   experiences rain most months of the year keeps
            this equipment.                           the area wet most of the time. Fagioli’s team leader
                                                      and along with HSE personnel were vigilant about
            Planning and Safety                       those unique site conditions and made it a priority
                                                      to ensure that workers stayed safe and took regular
            The core team of Fagioli Asia laid down a plan   breaks in designated shelter areas.
            documented in with a detailed schedule. Site   “As the team consisted of multinational and





























                                                                                               Picture 8 - Detail of the Acid
                                                                                               Gas Absorber before the
                                                                                               lifting operation


                                                                                 Impiantistica Italiana - Settembre-Ottobre 2019  45 45
   42   43   44   45   46   47   48   49   50   51   52