                                  FAGIOLI




                                  Morandi Bridge




                                  Removal Project













                                  After the collapse of Morandi bridge, Fagioli was called,
                                  together with other expert operators for the removal
                                  of Morandi bridge sections. Main temporary joint
                                  ventures  companies  for  this  project  are:  F.LLI  OMINI,
                                  which has been appointed as the Head of the group;
                                  IPE PROGETTI, experts in structural and architectural
                                  design; IREOS, specialized in environment services and
                                  for over 15 years,  in environment reclamation.
                                  Fagioli with its high level engineered equipment is coope-
                                  rating for the lowering operations of the sections which
                                  did not breakdown and represented a serious danger for   On  the  9th  of  February  2019,  Fagioli    managed  to
                                  the surroundings. Fagioli put on the table its engineering   execute the first step of the demolition operation of
                                  capacity to handle this huge concrete sections weighing,   Morandi Bridge in Genova. After the meeting with Italian
                                  in some cases, more than 1,000 ton. Fagioli used  tower   Prime Minister Conte and main National authorities,
                                  lift and strand jacking system (with strand capacity up to   held during the morning of the 8th of February, Fagioli
                                  600 ton each), SPMTs to mobilize the sections at ground   started the operation of lowering the first central bridge
                                  level; Crawler cranes used either for the lifting / lowering   section weighing about 900 ton, with a length of about
                                  of material and as a support for Fagioli equipment; gantry   36 m and 18 m wide and successfully completed the
                                  lifting system and modular trailers.     operation. A delay in the operation was due to weather
                                  First operation, february 2019           condition, a strong wing which postponed the lowering
                                                                           action. Fagioli used No. 4 x 600 ton capacity strand
                                                                           jacks (No. 2 strand jacks on the Western side bridge
                                                                           pylon  and  No.  2  on  Eastern  side  bridge  pylon)    to
                                                                           lower the central bridge section. The jacks used for
                                                                           the lowering operation were positioned onto cantilever
                                                                           beams provided with additional No. 4 strand jacks (180
                                                                           ton capacity each) with the task of balance the whole
                                                                           structure. No. 2   support beams were transversally
                                                                           positioned  underneath  the  western  and  eastern
                                                                           bridge pylons in order to anchor all the lifting/lowering
                                                                           structure to the  w/e bridge sections. On  the eastern
                                                                           bridge pylon another structure was positioned at the
                                                                           top end of the bridge with No. 2 additional strand
                                                                           jacks with counterweights with the task of providing a
                                                                           counterbalancing action during the lowering (Please see
                                                                           picture “operations”)
                                                                           After the removal of some of the sections and the neces-
                                                                           sary environment reclamation,  it was decided to explode
                                                                           some of the pylons (not in Fagioli scope of work). At the
                                                                           time being, all the sections and pylons of the Morandi
                                                                           bridge, have been successfully removed.