Picture 11 - Lifting operation

            from the manual, the same would be discussed,
            agreed and documented with the authorised Client
            representative on site.


            SPMT Engineering
            Transport drawings for each module were created
            keeping in mind recommendations from the
            client. Three point longitudinal  triangle and four
            point rectangular hydraulic configurations were
            considered for most of the transport operations.
            Suggestions from Fagioli site team were always
            respected and accommodated wherever possible.

            Lifting Plan
            Crane lift plans were studied well in advance
            and  was  finalised  to  consider  minimum  change
            in configurations. Also the cranes to be used in
            different areas of the Tangguh Expansion project
            were identified and implemented well in advance
            for maximum utilization of the resources.  Picture 12 - Lifting operation (Detail)

            Rigging Arrangement                       Considering the long mobilization period for the
                                                      items  to  Tangguh  site,  it  was made  sure that  all
            Rigging arrangement drawings were prepared   rigging  design were  performed  considering  the   Picture 13 - Detail of the
            considering maximum safety and best practices.   items available at site           rotation of the item
































                                                                                 Impiantistica Italiana - Settembre-Ottobre 2019  47 47