Further to executing the FEED, Amec Foster
The PMC organization:Wheeler also provided the license and the basic
design package for the delayed coker unit, which
overviewwill use the company’s leading Sydec delayed
coking technology. PMC work is intended to supplement the action
The EPC (Engineering, Procurement and and the resources of clients in managing large and
Construction) contract was awarded in May complex contracts. Various possible patterns are
2013 to an association of contractors led by encountered on the EPC market, ranging from
Tecnicas Reunidas (Spain) and an almost complete delegation
partnered by Saipem (Italy), GS of technical and contract
Engineering (South Korea) and administration matters to the
Itochu Corporation (Japan). The refinery is scheduled PMC, to intermediate situations
The Project Management to achieve commercial in which clients remain directly
Consultancy (PMC) contract completion, including a involved to various extents and
performance test of the
was awarded to Amec Foster refinery, in April 2018. then delegate the operations
Wheeler, who supplied The phased mechanical requiring extensive resources to
experienced technical and completion of the refinery the PMC. This is rather common
management resources to in companies that, like STAR,
manage the contractors. The maintain a direct operating
project financing is assured by interest and participation
an international pool of lenders, over a period of one and through the life cycle of the
coordinated by UniCredit and a half year allows for a investment.
supported by several ECA’s commissioned driven Further to the above, large EPC
(South Korea, USA, Japan, schedule completion. businesses may have complex
Spain, Italy). geographies, clients are often
The refinery is scheduled to headquartered away from
achieve commercial completion, the project site, contractors
including a performance test of are frequently associated in
the refinery, in April 2018. The multi-national joint ventures or
phased mechanical completion of the refinery consortia and the PMC is also often provided
over a period of one and a half year allows for a by multi-national engineering contractors. This
commissioning driven schedule completion. The requires a careful selection of the location where
contractors’ overall progress is currently (April the PMC activities need to be displayed. The
2015) around 22%, with engineering at substantial PMC needs to be close to the client and at the
progress, most of the important long lead same time, close to the heart of the project during
equipment under manufacturing and construction engineering, procurement and construction.
seeing the start of concrete works after the site While the construction PMC must remain on
preparation has almost reached completion. the jobsite, engineering and construction offer
Fig. 3 - South view with new
naphtha tanks