engineers for implementation. management and coordination total around 45.
Further to the normal commenting and review The number of Amec Foster Wheeler engineers
activity of the documents, upon issue, there and designers engaged in the document review
are other processes, such as Hazop (HAZard and commenting in the back offices is in the order
and OPerability analysis) and 3D model reviews of 80-100.
which result in a large amount of documentation
(1,000 P&ID’s to undergo Hazop, as an Construction, commissioning
example). To perform such tasks, team missions and start up
at the EPC contractor’s offices (Madrid, Milan,
Seoul) are planned and actuated. Their duration Due to the gigantic site preparation work, the jobsite
is of several months each time they occur. was populated very early and has been dedicated
Resourcing requirements are met by involving to earth moving and civil basic activities (grading,
other offices of Amec Foster Wheeler such as retention walls, underground mains) as well as to
Chennai (India) as support to the base team, so field facilities for over a year now.
that they can continue with the on-going project The organizational model of PMC at site was
requirements naturally more conventional than at the home
The materials management cycle review is less office, with an organization that essentially mirrors
demanding in regards to manpower, being the one of an EPC contractor’s management and
limited to the review of procurement procedures supervision and has all of the resources displayed
and terms for compliance with the contract (the at the jobsite.
technical evaluation summaries are reviewed under The site PMC team, managed by Amec Foster
engineering). Wheeler, foresees over 70 positions, 30% of
More critical is the PMC inspection work (at its early which will be STAR direct personnel. The majority
progress at the moment), where PMC inspectors of site PMC resources are locally employed, with
oversee manufacturing, factory tests and deliveries only a few positions covered by expatriated
of equipment and materials on behalf of STAR. personnel from the European offices of Amec
The number of Amec Foster Wheeler members of Foster Wheeler.
the Directorate in Madrid with responsibilities for
Sandro Venerus
Sandro, graduated in Chemical Engineering at the ent sectors among which Project Engineering, Pro-
Politecnico in Milano in 1976, is Senior Project cess, Proposals, Sales and Project Management.
Manager in the Contract Operations of Amec Fos- Through well over 30 years in the business Sandro
ter Wheeler in Milan. He started his career in the has explored the main aspects of engineering and
company in 1977 and has worked in several differ- contracting of process plants.