Page 17 - Impiantistica Industriale
P. 17

Cogen Project




            in Singapore






            Successful modularisation and project execution


            Stefano Occhetta, Amec Foster Wheeler




















                                                                                   Cogen Project

                                                                                   The objective of the Cogen Project (CP) is
                                                                                   to provide new combined power and ste-
                                                                                   am generation facilities to improve energy
                                                                                   efficiency and improve overall site com-
                                                                                   petitiveness.  The  new  facilities  will  help
                                                                                   the  site  create  and  capture  efficiencies
                                                                                   associated with generating power onsite
                                                                                   to offset import from the public utility grid
                                                                                   and shutting down existing utility boilers.
                                                                                   Amec Foster Wheeler’s scope is to design
                                                                                   and build the Cogen plant to produce po-
                                                                                   wer and steam for site consumption and
                                                                                   export via a new 66 kV (kilovolt) substa-
                                                                                   tion. The CP scope is predominately lo-
                                                                                   cated on brownfield sites and consists of:
            3D rendering of Cogen 1 and Cogen 2 Power Islands
                                                                           •   Two power islands including:
                                                                               -   Two gas turbine generators
                                  Introduction                                 -   One modularised high voltage substation
                                                                               -
                                                                                   Two modularised heat recovery steam
                                  Brownfield cogeneration plants which are integrat-  generators
                                  ed with process plants, are typically field erected   -   Two natural gas compressors
                                  projects,  where  modularisation  is  limited  to  the   -   One cooling tower
                                  delivery of some pre-assembled pressure parts of   -   16 modularised piperacks (PAR (pre-
                                  Heat Recovery Steam Generators (HRSG) and skid   assembled racks)/PAU (pre-assembled
                                  mounted equipment. One reason is that the cost of   units).
                                  modular units like HRSG, typically ordered together   •   New import facilities to supply the site with na-
                                  with other long lead items during FEED (front end   tural gas
                                  engineering design), is generally higher than field   •   Modification to the existing utility boilers, ste-
                                  erected units since modules are designed to with-  am load shedding on existing process and
                                  stand the rigors of shipping and require more struc-  utility systems, interconnecting piping, modi-
                                  tural steel. Another reason is that the balance of   fications  to E&I  (electrical  & instrumentation)
                                  plant is heavily dependent on vendor information,   systems.
                                  thus limiting the opportunities for pre-assembled   •   Civil and underground works have been mas-
                                  piperacks  and  substations  once  the  EPC  (Engi-  sive:
                                  neering, Procurement, Construction) is sanctioned.   -   600 piles
                                  This article outlines the success story of a cogene-  -   25,000 m3 of soil excavated largely by
                                  ration project Amec Foster Wheeler has designed   hand in presence of several underground
                                  and built with a full modularised approach.      known and unknown assets in service



                                                                                 Impiantistica Italiana - Settembre-Ottobre 2017  15
   12   13   14   15   16   17   18   19   20   21   22