Page 22 - Impiantistica Industriale
P. 22

Stage 6 – Module execution
                            phase

                            During this stage of the project, detailed enginee-
                            ring was carried out to finalise module design and
                            build.
                            The Project Execution Plan for the module execu-
                            tion phase considered the following issues:
                            Engineering
                            •   Accelerated engineering activities compared
                                with a conventional approach. In particular,
                                structural design required a greater effort at
                                the commencement of this phase;
                            •   Foundation and underground design should
                                incorporate module, crane and transportation
                                requirements;
                            •   Documents and drawings shall be produced
                                on a module-by-module basis, in alignment
                                with the needs of the construction schedule,
                                and must address the detailed module design
                                requirements, such as cable routing, hook-up
                                access, etc.  Each module was set up as one
                                or more separate construction area(s) in the
                                project to facilitate this.
                            •   Weight management and centre-of-gravity con-
                                trol throughout the module execution phase;
                            •   Module envelope management;
                            •   Multiple critical paths and sequences within
                                the schedule.
                            Procurement
                            •   Accelerated procurement activities compared
                                with the conventional approach;
                            •   More material take-offs and purchase order   Legs-down PARs on SPMT
                                top-ups should be anticipated;
                            •   Equipment and bulk materials, needed early
                                for free issue to module fabricators, at several   dule-building focused on early punch out and
                                locations.                               completion of modules and their associated
                            Construction                                 hook-up spools;
                            •   At the fabrication yards, management of mo-  •   Pre-commissioning at the mechanical module
                                                                         yards, including chemical cleaning;
                                                                      •   Functional electrical tests at the substation
                                                                         module yard;
                                                                      •   At the plant site undergrounds and paving
                                                                         completed before modules are transported to
                                                                         the corresponding area;
                                                                      •   Transportation and handling of the modules,
                                                                         with detailed plans covering all interfaces, to
                                                                         ensure safe and timely installation;
                                                                      •   Plan to manage out of sequence delivery of
                                                                         modules;
                                                                      •   Hook-up phase treated as a major plant ‘tur-
                                                                         naround’.
                                                                      Detailed engineering, procurement, subcontrac-
                                                                      ting, construction, pre-commissioning and support
                                                                      to owner commissioning and start-up have been
                                                                      executed in work sharing by Amec Foster Whee-
                                                                      ler’s Milan and Singapore home offices, bringing
                                                                      together the experience of Milan on Cogen and
           Legs-up PARs loaded on the barge                           modular plants and Singapore’s knowledge of the


       20  Impiantistica Italiana - Settembre-Ottobre 2017
   17   18   19   20   21   22   23   24   25   26   27