associated to long transmission
                                                                                      systems could be an asset for the
                                                                                      energy renaissance of the sub-Saha-
                                                                                      ra region, with social and economic
                                                                                      development of its inhabitants.
                                                                                      From studies on the development of
                                                                                      long DC transmission systems in Afri-
                                                                                      ca [7], the figures 11 and 12 show
                                                                                      the cost relevant to the transmission
                                                                                      for the delivered kWh and the total
            Fig. 10 - Some eco towers in Italy, France, US and South Africa           cost of delivered kWh as a function
                                                                                      of the production cost; this with 2
                                  an huge but largely unexploited potential of both   main extreme hypotheses relevant to annual ra-
                                  fossil and renewable resources, which, connected   tes (AR) and cost of losses (CL). The 6% value of
                                  to the development of powerful/long transmission   AR corresponds to a discount rate close to 3.5-
                                  systems, could create strong inter-regional exchan-  4% over 25 years, as indicated by IMF for special
                                  ges of electrical energy. This could bring substantial   projects with grants/soft financing, while the 10.5
                                  contributions to the eradication of poverty and ac-  % is related to private financing.
                                  cess to electricity to 600 million people of the sub-  Considering the huge hydro potentials in those
                                  Sahara region. The construction  of hydro power   countries (RDC with Inga, Ethiopia, Cameroon, An-
                                  plants, or of power plants in general, and of OHTLs   gola) and the large new gas discoveries, appropria-
                                  is a labor intensive activity providing local jobs.  te utilization of these resources to feed different re-
                                  Considering the hydro potential with the economic   gions in sub-Sahara seems mandatory (figure 13).
                                  development of large plants with high load factors   With a 2 c$/kWh production cost (cheap large
                                  and the discovery of enormous gas reserves (e.g.   hydro), electricity can be delivered at 3÷3.5 c$/kWh
                                  Mozambique), which could provide cheap con-  for 1000 MW at 1000 km or 4000 MW at 3000 km.
                                  ventional electricity in some areas, possible plants   With a 4 c$/kWh production cost (GTCCPP with





















            Fig. 11 - Transmission cost of delivered kWh on the AC side of the receiving end; optimum voltage level for different powers (P) and length [7]




















            Fig. 12 - The cost of energy delivered on the AC side of receiving end as a function of generation cost [7]