Page 31 - 62
P. 31

Fig. 4 - Modularized radiant coils hanged on top   Fig. 5 - The biggest module (still uncompleted) during site
            part (arch) inside their temporary frame structures  prefabrication in the pre-turnaround phase

            input to a specific turnaround planning software tool,   smaller pieces to be assembled in field. In details:
            able  to  manage  in  detail  all  thousands  of  single  site   I)   the new coils for radiant sections were thus
            activities, concerning all fields: fabrication, lifting,   completely assembled inside two frame structures,
            scaffolding, quality inspections etc.        which were appositely erected in a laydown area
            Vergaengineering was directly involved in the use of   within the refinery (figure 4). The site was so
            such highly specialized software tool, during both the   windy, that the tall frame structures had to be
            planning phase and the site works phase for the   constructed with high structural standards, and
            consequent updates during step-by-step erection   also a temporary foundation was required for the
            completion.                                  circumstance;
                                                     II)   the  convection  coil  replacement  did not  require
                                                         particular activities during pre-turnaround site
            Procurement, fabrication and                 activities, as the new prefabricated coil sectors
            transportation phase                         were already tested at workshop;
                                                     III)  the highest effort was for the construction of the
            Fabrication phase was partially overlapped to   big air pre heater modules. These items were
            engineering and planning phase. Fabrication also had   assembled in a laydown area very close to the
            some  back-inputs  on  engineering,  and  consequently   plant to be revamped, in order to minimize the
            on planning, which allowed further improvement of the   crane operation range due for lifting of modules in
            design.                                      final position.
            The main challenge related to fabrication was the      The modules contained all structures, platforms,
            coordination  of  the  workshops  spread  throughout   ladders, tubing, piping and equipment. Moreover,
            Europe (mainly: Italy, Romany, Finland, Poland, Belgium   to optimize the scaffolding effort, some parts of
            and Netherlands) to allow the fabricated items arrive at   scaffolding were left in place once the modules
            site yard at proper time. In fact, both delay and advance   were finished: this allowed to avoid the
            were to be avoided, as the restricted site layout needed   re-installation of scaffolds needed for the last
            to be timely fed, to achieve schedule construction   mechanical and paint adjustments of assembled
            without space obstruction.                   system after its final positioning.
                                                         A further challenge arose from modules weight.
                                                         Since a temporary foundation had to be avoided,
            First site phase: pre-turnaround             Vergaengineering designed a temporary flooring

            Vergaengineering site jobs started five months before   structure, which properly distributed the modules
            turnaround. In fact the prefabricated modules were so   weight on the ground. This flooring structure was
            big and heavy, which could not travel across the   anchored to removable concrete panels through
            continent. Consequently, these were fabricated in   hundreds of bolts (figure 5).


                                                                                    IndustrIal Plants - May 2018
                                                                                                                   27
   26   27   28   29   30   31   32   33   34   35   36