Fig. 5 - Technical Area with Pure Water Storage installation


                            Bauleiter (Construction Manager): Baulaiter is also
                            declared to the local authority in the Building Permit  Construction and
                            official form and appointed by the building owner   commissioning & qualification
                            prior the site construction work start.
                            The Bauleiter (Construction Manager) shall be also  completion highlights
                            supported by different  FachBauleiter with spe-  Construction team mobilised at site was supervi-
                            cial competences with regards of Electricity, Fire   sing all the construction works as from the civil and
                            Protection, TGA (Technisch Gewerbliche Abend-  structural construction up to the system handover
                            schule) to ensure that the building construction is   to Bracco.
                            executed, for all discipline, in accordance to the   Safety remained the first project priority and the fa-
                            applicable laws and regulation. FachBauleiter can   cility has been realised with a successful HSE (He-
                            be also provided by the engaged construction con-  alth Safety Environment) program implementation
                            tractors (civil, mechanical and electrical). That was   and management. Finally, no LTIR (Lost Time Injury
                            the case during the construction of the new quality   Rate) during the 15 months of construction were
                            control laboratories.                     recorded.



                  Nuovo complesso di Controllo Qualità

                  in Germania


                  Bracco e Amec Foster Wheeler (ora Wood) hanno realizzato un nuovo complesso di Controllo Qualità presso
                  Singen (Baden Württemberg, Germania) a servizio dell’impianto esistente di fill finish relativo a liquidi di
                  contrasto per diagnostica.
                  Il progetto è stato seguito da Amec Foster Wheeler (ora Wood)  a partire dallo studio di fattibilità fino al
                  completamento delle attività di Commissioning, per un periodo complessivo di circa due anni. Le attività di
                  ingegneria si sono svolte principalmente a Milano, mentre a Singen, un team di supervisione dei lavori  di Amec
                  Foster Wheeler (ora Wood) coadiuvato da un team Bracco e Bipso per la parte di avviamento hanno consentito
                  il raggiungimento pieno degli obiettivi di qualità, schedula e costi prefissati.