Page 62 - 63
P. 62

Fig. 1 - Quality Control Labo-
       ratory Building W40 (in light
       green, centre of the picture)
       and electrical substation (in
       light green, bottom of the
       picture


                            the elevated bridge to the production building W20   rance of the facility, related to the  façade design
                            for easy logistic transfer of sample and materials.   and the office finishing.
                            The electrical substation (in light green, bottom of
                            the figure 1), including main equipment, has been
                            designed to allow possible expansion, in particular  Local and Regional Permit
                            considering  a  future high  automated warehouse   Process
                            and to cope with the electrical demand of the cur-
                            rent site.                                The purpose of this section is to provide an over-
                            Landscaping, roads and building accessibility were   view of the steps followed to obtain the authoriza-
                            designed to guarantee an optimal logistic, for ma-  tion to build and operate the facility.
                            terial needed by the site, as well as for the person-
                            nel working in the laboratory building.   Operating permit
                            Parking  requirements  were  considered  in accor-  The facility was authorised by third-party institution,
                            dance to the local regulation and to the workforce   namely Regierungspräsidium Tübingen, who shall
                            expected in the new facility. It is worth to mention   verify the compliance of the project with the local
       Fig. 2 -  South view of the   that Bracco was also supported by Dante Benini   entities (City of Singen, Fire Brigade, TÜV).
       Quality Control laboratory  Architect in the definition of the aesthetic appea-
                                                                      Building permit in Germany
                                                                      In the Baden Württemberg Region, as well in the
                                                                      whole Germany, the construction application pro-
                                                                      cess requires a Building Permit: this permit has to
                                                                      be formally issued by the owner of the new con-
                                                                      struction (BIPSO establishement in our case) and
                                                                      approved by the municipality. The application is
                                                                      usually evaluated and approved within a period of
                                                                      90 days. In case of substantial modification to the
                                                                      permit package, partial or complete resubmission
                                                                      might be envisaged.
                                                                      In most of the cases the application for a building
                                                                      permit is submitted to the local building authority
                                                                      by the building supervisory authority (Bauamt), that
                                                                      in our case was the Architect Studio Mussgnug-



       60  Impiantistica Italiana - Maggio - Giugno 2018