Page 24 - Industrial Plant 2015
P. 24

Fig. 2 – Polyethylene  containers, in both cases directly loaded on containers  •	 manage in parallel the execution of a megaproject
loop and gas phase     ships coming to Ruwais on daily basis.                         of five process plants, awarded in a highly
reactors               Massive dimensions in terms of quantities and numbers          aggressive arena of competitors, leading to the
                       give an idea of the complexity of the project. In              involvement of new and numerous suppliers on
                       particular, the most significant key parameters can be         an international scale;
                       summarized as follows:
                       •	 structural concrete: 205,000 m3;                      •	 manage an overheated vendor market in UEA,
                       •	 steel structures: 25,000 tons;                              MENA (Middle East and North Africa) region, as
                       •	 equipment: 27,000 tons;                                     well as in Korea, due to booming of investments
                       •	 piping isometrics: 50,000 nos;                              in UAE, where a large number of big projects were
                       •	 piping quantity: 1,600,000 inch dia;                        simultaneously awarded; congested conditions of
                       •	 control buildings and electrical substations: 13            ABU Dhabi port were also to be faced;

                             nos;                                               •	 scarcity in skilled workmen due to the large
                       •	 instrumentation loop checks: 31,000 nos;                    number of big projects simultaneously awarded in
                       •	 electrical and instrumentation cables: 4,300 km.            the UAE market;

                       These huge numbers have always been an area of           •	 constructing in a sandy environment like Ruwais
                       attention to focus on from the very beginning and have         for the first time in the world an LDPE plant
                       indeed motivated all participants in a passionate hard         peculiar on two counts, for the technical requisite
                       work for the success of this project.                          of the cleanliness of the materials, requiring a total
                       The plant reached the operation stage and started              absence of impurities (and sand) also invisible to
                       commercial production in 2014 (figure 2).                      the naked eye, and for the high pressure
                                                                                      technology in which the process fluids reach
                                                                                      pressure levels over 3,000 atm, demanding the
                                                                                      highest standard of quality and safety.

                                                                                Set at the dinner of the first team-building session in an
                                                                                eatery at the surrounding of Milan, we looked at each
                                                                                other and counted 11 people sitting at the same table,
                                                                                11 different nationalities. Rightly we thought that the
                                                                                biggest challenge was certainly going to be
                                                                                communication. Different languages, cultures,
                                                                                behaviors and style of life must live side by side,
                                                                                integrate and achieve one common goal: satisfy the
                                                                                expectations of everyone, from the end user through
                                                                                the 11,000 workers which populated at the peak the
                                                                                Ruwais Construction Site.

                       The challenges                                           The execution: key factors

                       Borouge 3 might have seemed a project to which “the      Construction-oriented engineering
                       road was paved” since it was about polymer plants,
                       well known technology to Tecnimont. It should have       The engineering started before the formal signature of
                       been a copy plant of Borouge 2, however the reality      the contract and were conducted and completed
                       proved to be far different. Brand new challenges were    throughout the project on the early schedule (figure 3),
                       launched:                                                also thanks to Tecnimont experience and expertise in
                       •	 implementing a contract with a joint venture          polymers units, in PE/PP Borealis and LDPE Basell
                                                                                technologies and in Borouge standards and
                             Korean partner, whose mindset is of a military     specifications. This anticipation was a key element to
                             imprint and who are extremely proud of belonging   provide sufficient room for the more difficult phases of
                             to a fast growth country;                          construction to follow.
                       •	 work with operating sites located in different area   In fact, the first P&IDs, as well as material requisitions
                             of the globe Milan, Malta, Seoul, Mumbai,          for critical items were issued as early as the 2nd month.
                             Braunschweig, Abu Dhabi and Ruwais;                The 3D modeling was also done much earlier than
                                                                                normal and by month 18th, 90% 3D model was ready.
                                                                                This gave a distinctive advantage to the procurement
                                                                                and construction phases.
                                                                                This approach resulted to be successful in providing

               Industrial Plants - May 2015