Page 24 - Industrial Plant 2015
P. 24
Fig. 2 – Polyethylene containers, in both cases directly loaded on containers • manage in parallel the execution of a megaproject
loop and gas phase ships coming to Ruwais on daily basis. of five process plants, awarded in a highly
reactors Massive dimensions in terms of quantities and numbers aggressive arena of competitors, leading to the
give an idea of the complexity of the project. In involvement of new and numerous suppliers on
particular, the most significant key parameters can be an international scale;
summarized as follows:
• structural concrete: 205,000 m3; • manage an overheated vendor market in UEA,
• steel structures: 25,000 tons; MENA (Middle East and North Africa) region, as
• equipment: 27,000 tons; well as in Korea, due to booming of investments
• piping isometrics: 50,000 nos; in UAE, where a large number of big projects were
• piping quantity: 1,600,000 inch dia; simultaneously awarded; congested conditions of
• control buildings and electrical substations: 13 ABU Dhabi port were also to be faced;
nos; • scarcity in skilled workmen due to the large
• instrumentation loop checks: 31,000 nos; number of big projects simultaneously awarded in
• electrical and instrumentation cables: 4,300 km. the UAE market;
These huge numbers have always been an area of • constructing in a sandy environment like Ruwais
attention to focus on from the very beginning and have for the first time in the world an LDPE plant
indeed motivated all participants in a passionate hard peculiar on two counts, for the technical requisite
work for the success of this project. of the cleanliness of the materials, requiring a total
The plant reached the operation stage and started absence of impurities (and sand) also invisible to
commercial production in 2014 (figure 2). the naked eye, and for the high pressure
technology in which the process fluids reach
pressure levels over 3,000 atm, demanding the
highest standard of quality and safety.
Set at the dinner of the first team-building session in an
eatery at the surrounding of Milan, we looked at each
other and counted 11 people sitting at the same table,
11 different nationalities. Rightly we thought that the
biggest challenge was certainly going to be
communication. Different languages, cultures,
behaviors and style of life must live side by side,
integrate and achieve one common goal: satisfy the
expectations of everyone, from the end user through
the 11,000 workers which populated at the peak the
Ruwais Construction Site.
The challenges The execution: key factors
Borouge 3 might have seemed a project to which “the Construction-oriented engineering
road was paved” since it was about polymer plants,
well known technology to Tecnimont. It should have The engineering started before the formal signature of
been a copy plant of Borouge 2, however the reality the contract and were conducted and completed
proved to be far different. Brand new challenges were throughout the project on the early schedule (figure 3),
launched: also thanks to Tecnimont experience and expertise in
• implementing a contract with a joint venture polymers units, in PE/PP Borealis and LDPE Basell
technologies and in Borouge standards and
Korean partner, whose mindset is of a military specifications. This anticipation was a key element to
imprint and who are extremely proud of belonging provide sufficient room for the more difficult phases of
to a fast growth country; construction to follow.
• work with operating sites located in different area In fact, the first P&IDs, as well as material requisitions
of the globe Milan, Malta, Seoul, Mumbai, for critical items were issued as early as the 2nd month.
Braunschweig, Abu Dhabi and Ruwais; The 3D modeling was also done much earlier than
normal and by month 18th, 90% 3D model was ready.
This gave a distinctive advantage to the procurement
and construction phases.
This approach resulted to be successful in providing
Industrial Plants - May 2015
22