Page 25 - Industrial Plant 2015
P. 25

Fig. 3 - Home Office
                                                                                                                   Services Progress
                                                                                                                   Curve

                                                                                                                   Fig. 4 - Use of 3D
                                                                                                                   model to analyze the
                                                                                                                   feasibility of the
                                                                                                                   erection works
                                                                                                                   sequence

feasible and look-ahead work-fronts for the construction  commissioning, commissioning and start-up.
subcontractors, which were also supported by an           Particular attention was dedicated to the LDPE Unit,
extensive use of the 3D model tools. All material         where the high pressure technology demands for
availability, piping prefabrication status and actual     absolute trouble-free startup. In addition, the super
erected quantities have been introduced in the 3D         clean product of the wire and cable technology requires
model database so to have a visible and active control    the highest level of cleanliness from manufacturing up
over the erection feasibility in such congested process   to the final commissioning stage. The experience
units and to sustain an efficient sequence of erection    gathered by Tecnimont in previous LDPE installations
(figure 4).                                               has proved to be fundamental for this purpose.

Lessons learnt                                            Procurement strategy

During the first months of the project, the experiences   The joint venture made an aggressive procurement
learned in previous projects from Borouge, Tecnimont,     campaign based on the below strategic decisions and
TPI and Samsung Engineering were shared over              actions implemented by the respective operating
several joint working sessions. The results of the        centers of Milan and Seoul, where the procurement
discussions were subsequently incorporated in the         execution was directed. In particular:
design and methodology of construction, pre-              •	 early placement of purchase orders for the