Page 26 - Industrial Plant 2015
P. 26
previously identified long lead items, like plastic construction subcontractor, represented a key asset
extruders, main compressors and process for the joint venture, especially in meeting the highest
reactors, pneumatic transport, high pressure demand of flexibility imposed by the typology of the
equipment and others; works and in the proactive approach put in place to
• ensuring booking of some raw material in an handle interfaces among subcontractors.
overheated market quite early in the project; Direct manpower injections have been extensively
• large use of vendors already adopted in Borouge used by the joint venture as countermeasure to boost
2 project case, as well as vendors adopted by the progress in specific activities and to sustain
other contractor in projects for other Adnoc subcontractors performance to achieve the challenging
Companies, to maximize previous positive targets set up by the project needs. Moreover, the joint
experiences, long term reliability equipment and venture has also introduced engineers in subcontractors
availability of efficient post sales services; organizations to make sure the correct understanding
• placing of frame agreements with selected of contractor deliverables and expectations in specific
vendors for specific items, as proactive approach tasks.
to material standardization requirement and better
control over sub-vendor performances; HSE performance
• advance availability of material for steel structures
erection and pipe fabrication was available on site Safety, environment and the wellbeing of all the
as per the feasibility curves shared with erection individuals building the plant were of paramount
subcontractors; importance for the Tecnimont and Samsung
• extensive sessions of Factory Acceptance Tests Engineering, as well as for all the stake holders,
for DCS (Distributed Control System) and related Borouge at first. The contractors and subcontractors
control logics in the vendor premises together complied not only with the HSE (Health Safety
with process and automation project leaders, to Environment) standards of the Adnoc Group, but they
assure a positive performance of interlocks and took several new initiatives in this respect.
functional checks during commissioning stage at Incident Injury Free program, incentives, safety awards
site. and many similar initiatives assimilated the “safety first”
message to all the personnel bringing a culture of
Subcontracting strategy safety awareness in the entire project. A permanent
training center was established at site by contractor
The construction works were implemented through a where all the employees, including vendors and labors,
pool of specialized subcontractors splitting the overall have been specifically trained to be able to safely cope
scope of work by discipline, such as civil, mechanical, with the tasks they were called for. The below
electrical and instrumentation. This approach was recognition of intermediate safety achievement was
mainly dictated by the need of finding valuable and distributed to all the thousands of people present at
enough resources in the market and by the intention to site, as sign of appreciation of their attitude versus
minimize the risk of failure of a general subcontractor to safety on site.
handle wide portion of works under stringent project The project finally reached 65 mil worked manhours
requirements from several perspectives. without LTI (Lost-Time Injury), a remarkable
Tecnimont ICB, the totally owned Tecnimont achievement in this field, with over 11,000 people
Fig. 5 - Medallion for
achieving 45 million
MHrs without LTI
(Lost-Time Injury)
Industrial Plants - May 2015
24