Page 27 - Industrial Plant 2015
P. 27

working at site at the peak of construction (figure 5).

Quality Control

The EPC Contractor along with its construction
subcontractors and with the active participation of the
PMC and Borouge were successful in breeding a
culture of high quality standards, through some
essential initiatives, including checking of piping
internals with boroscope (figure 6), large use of
microscope to detect impurities, stringent audits and
zero tolerance policies.
The level of welding defects at site was a clear example
of the results achieved: the weld repair rate was
significantly lower than the normal industry standards.

Constructability                                             SIMOPS (SIMultaneous OPerationS)                           Fig. 6 - Quality checks
                                                                                                                        on equipment
Detailed constructability studies were carried out           The introduction of hazardous substances like              internals
during the beginning phase of the project in the most        hydrocarbons, in five adjacent process Units at different
critical activities, like underground works and heavy lifts  stages of the project, requires advanced detailed          Fig. 7 -
(figure 7). The proper implementation of this tool,          analysis to prevent any possible accident, putting in      Constructability
involving construction knowledge and experience in           place all the necessary countermeasures to allow           studies for installation
planning from design to startup stage, resulted to be        construction, commissioning and start-up activities to     of main equipment
fundamental to plan the most efficient and effective         be carried out simultaneously in the same area.
sequence of erection during the subsequent                   The SIMOPS (SIMultaneous OPerationS) assessment
construction works.                                          was conducted through several dedicated
The site activities were also subject of regular “cold eye   interdisciplinary (commissioning, construction, site
review” carried out by senior representatives of both        HSE) meetings. The mitigation actions identified in the
joint venture partners organization, with wide               SIMOPS assessment meetings were continuously
experience in construction and commissioning of large        reviewed, and the implementation progress was
packages. The goal of this review was to ensure proper       monitored by site HSE together with PMC and Borouge
proceeding of the EPC activities, especially in light of     representatives, party releasing any Permit to Work in
their past performances on similar projects, and to          the area affected by hydrocarbon.
minimize the risk of deviating from the right pace of        All the resulting HSE hazards have been assessed and
required progress.                                           appropriate control levels have been implemented to