Page 99 - impiantistica_3_2015
P. 99
Table 3 - Asset register RAM modeling assumptions.
The full supply chain (FSC) model base case main
The model construction in Optimise© involved outputs are summarizing in table 4:
the equipment configuration, as assumed by the From this first set of results, it can be concluded that
RBD and reliability data, as assumed by the asset over the 25 years, in average, the unit will be able
register. The Bureau Veritas software Optimise© to produce for about 90% of the time. Each year,
has also been used to model a number of more the unit will stop its production for a bit less than 36
complex scenarios using a modeling artefact called days because of unplanned shutdowns (random
“conditional logic”. Conditional logic, defined by failure of equipment), preventative maintenance,
simple Boolean logic has been used to model: time to restart after a shutdown and spurious trips
• gradual subsea / plant restarts following of safety systems. This general information will help
to operator to develop its pricing strategy based on
failures; the potential income the unit will generate as well
• delayed repair for some particular equipment; as to have an appreciation of the productivity of its
• interconnected / common equipment (e.g. installation.
Following that, the operator needs to know what
for instance if two sets of heat exchangers are the most critical systems in order to understand
are sharing a common spare, once the spare which modifications in the design or in its IMR
is used a subsequent failure will result in a strategy will impact the most the availability of the
complete interruption in production); unit in a positive manner. Figure 8 identifies the
• equipment / system bypasses (e.g. due to non top 5 systems or events that contribute the most
critical or partially critical equipment); to overall production losses:
• voting, 2 out of 3 (2oo3) (e.g. in a dehydration As presented in figure 8, the liquefaction unit is the
system where one of three dehydrator main contributor to FLNG project downtime. Based
columns is in regeneration duty at any one on this information, operator knows now that any
time, failure of one of the units will cause a improvement performed on this unit will impact in
reduced throughput capacity to 50%); an effective manner the availability of the whole
• impact of cyclones / metocean on the project.
production system and offloading system; For instance, as the losses in production within
• impact of planned and preventative liquefaction system are mainly driven by gas
maintenance (specially for gas turbines, turbines and compressors failures, modification in
compressors and dehydration & mercury bed). the design can be studied in a separate sensitivity
case in order to assess impact on availability
RAM results but also to understand cost associated with the
implementation of the new components (i.e.
In order to establish average results and confidence electric motors instead of gas turbine or additional
levels, the RAM model was run for 1,000 individual turbo compressors for a higher redundancy).
lifecycles considering 25 years as the system life. Inspection strategy for the topsides induces
The following presents and discusses some of
the outputs of the study based on the previous
Table 4 - FLNG FSC
summary results
Impiantistica Italiana - Maggio-Giugno 2015 97