Page 100 - impiantistica_3_2015
P. 100
Fig. 8 - FLNG FSC system about 18% of the overall losses. Based on this or a different repair or maintenance strategy to
criticalities – Top 5 information, operator will be able to reassess IMR reduce the repair time or restart time.
strategy in order to investigate if some components Most of the other systems were accounting for less
Fig. 9 - FLNG equipment can be inspected or maintained in a shorter period than 2% of the overall losses. It has been concluded
items criticalities of time or simultaneously with particularly long that any action performed on this remaining
repairs predicted by the RAM model. systems will then only increase the availability of the
Subsea equipment of field A represents also unit in a very limited way and often, for a very high
about 18% of overall losses of the FLNG project. cost. By proceeding in a transverse analysis i.e.,
As interventions on well equipment items can not by system but by type of equipment, the main
be extremely long to be carried out because of equipment items contributing the most to the loss
Mobile Offshore Drilling Units (Modu) mobilization, of availability were also analyzed (figure 9).
operator will have to concentrate on the availability This transverse view allows the operator to give
of Modu near the field to optimize mobilization time. a priority for its IMR strategy. Detailed analysis
Operator will also assess as precisely as possible performed presented also many other outputs
the wells capacity to ensure main producing wells such as the number of maintenance mobilization
will less be impacted or at least that production can associated with the type of mobilization (crew, ISV,
be maintained in a partial manner. Modu etc.) in order to provide a good basis for the
“Restarts”, that corresponds to the ramp-up Operational Expenditure (Opex) allocations.
state when to installation has been completely Similarly, annual production availability as well
shut downed, contributes to 6% of overall losses. as production capacity duration per range of
A dedicated analysis has then been performed production capacity were presented in order to
to understand which equipment items were provide Operator with an efficient decision tool
responsible for the greatest number of restart based on level of production capacities (time where
in order to investigate either a change in the the unit produces between 0 to 0.25 mtpa, 0.25 to
configuration, additional bypasses when possible 0.5 mtpa, 0.5 to 0.75 etc.) and annual production
graphs impacted by extensive inspection scheme
or other periodic effects like cyclones. Annual
production allows also the operator to understand
the gravity of potential penalties that may be faced
in case they do not meet contractual requirements.
Conclusions
This paper presented the benefit of RAM analyses
for FLNG process optimisation, the detailed
methodology as well as an application of the
process. Even if very powerful and cost efficient,
the value of RAM is constrained by the lack of
available reliability data for such new installation and
by the ability to think ‘outside of the box’ to develop
worthwhile and value adding ‘what-if scenarios’. It
has been found that it is of the utmost important
to define clearly all the assumptions to be taken
into account and invest as much time as possible in
sensitivity cases to assess the different options but
also to valid successfully the design phases, not
only with the good design, but with the best one.
This paper was presented at the 12th Offshore
Mediterranean Conference and Exhibition in
Ravenna, Italy, March 25-27, 2015. It was
selected for presentation by OMC 2015
Programme Committee following review of
information contained in the abstract submitted
by the author(s). The Paper as presented
at OMC 2015 has not been reviewed by the
Programme Committee.
98 Impiantistica Italiana - Maggio-Giugno 2015