Page 25 - Impiantistica Italiana
P. 25

tions for cooling water,  light gasoil
                                                                                      and slurry
                                                                                  •   New gasoil blender unit
                                                                                  •   New analyzers house
                                                                                  •   Extensive revamp by addition of new
                                                                                      pipe-racks and interconnecting pi-
                                                                                      ping in offsite
                                                                                  •   Extensive revamp of electrical and in-
                                                                                      strumentation networks
                                                                                  •   Relocation of steam let-down station.
                                                                                  The Engineering activities  lasted till the
                                                                                  end of 2014 and were developed mainly in
                                                                                  our Milan and Chennai offices.
                                                                                  A robust client team, composed of mana-
                                                                                  gers and technicians from Total were re-
                                                                                  sident on a permanent basis in Milan for
                                                                                  almost a year to facilitate the preparation
                                                                                  and the issue of engineering deliverables
                                                                                  and to speed-up by vis-à-vis meetings the
                                                                                  resolution of the problems encountered
            High-Pressure Steam Boilers Unit                                      during detailed design.
                                                                                  In addition, several visits to the Milan office
                                                                                  were performed by Antwerp Refinery per-
            sidue import units were cancelled.  •   Direct construction:   1.6MM mhrs  sonnel to verify the compliance with stan-
            The execution of the OPTARA Project was                               dards and procedures.
            divided by Total in several lots, assigned to   The scope of the high-pressure boilers   The Chennai Office was mainly responsi-
            different EPC Contractors. As part of this   unit 23 was the production of high pres-  ble of the sour water stripping and high
            process, the contract for the execution of   sure  steam  to  meet  the  increased  de-  -pressure boiler units and its activities and
            the LOT3A was awarded to Foster Whee-  mand  by  new  and                              performance were
            ler (now Wood) Milan office in May 2013.  existing  users.  It  The LOT3A consisted    constantly monito-
            The contract was assigned on a lump-sum   consists of four new                         red through mee-
            basis for engineering and procurement   independent  boi-  of three main packages:     tings, visits and by
            services, while construction supervision   lers,  manufactured“Grass-roots Steam       resident coordina-
            services  were on a reimbursable basis.   and  supplied  by                            tor.
            Materials  and  construction  works  orders   BBC (Belgium Boiler   Boiler, Brown-field new   Since a large por-
            were placed directly by Total.     Company), each-one    Sour Water Stripper and       tion of the scope
            The scope of work finished at the Ready   with a capacity of 30   Off-sites and Utilities   of work was related
            for Commissioning phase.           tons per hour of ste-                               to the revamp of
            As part of the scope, we also prepared   am.                                           existing  facilities,  a
            a Class II cost estimate, which was then   The  Sour  Water                            team  composed  of
            used  as baseline for  the control  of the   Stripper was designed to strip-off hydro-  engineers and draftsmen of piping, civil,
            project costs.                     gen sulfide (H2S) and ammonia (NH3) and   electrical and instrument disciplines was
            LOT3A consisted of the following three   to reduce their con-
            main packages that were developed star-  centration respectively
            ting from the FEED (front-end engineering   to 10 ppmw and 50
            design) prepared by another company:  ppmw from sour water
            •   Grass-roots Steam Boiler (HPB   produced by revamped
                -#U23)                         ARDS and MHC units.
            •   Brown-field new Sour Water Stripper   The Off-site and Utili-
                (SWS-#U99)                     ties covers almost 80%
            •   Off-sites and Utilities (O&U-#U00)   of the overall scope
                                               and  includes  new  fa-
            The most significant construction parame-  cilities and modifica-
            ters of the projects are the following:  tions of existing ones
            •   Piles:            1600         necessary to support
            •   Concrete:         4500 m3      the new refinery confi-
            •   Piping:           2500 tons    guration.
            •   Steel structure:   1300 tons   Among the most im-
            •   E/I cables:       155 km       portant areas of inter-
            •   Equipment:        43           vention, we can list:
            •   Modules           9            •   New natural gas
            •   Overall project:   42 months       import station
            •   Construction span:   28 months  •   New pumping sta-  Natural Gas Import Station



                                                                                 Impiantistica Italiana - Settembre-Ottobre 2018  23