            operation. They were issued several documents   tracks . Fagioli high performance skidding system
            and studies after an in-depth analysis of the ground   is designed to self-load and move items horizon-
            capacity around the installation area: levelling acti-  tally  from one location to another. Steel structure
            vity was executed with sand and crusher-run ma-  of the skid system is composed by a Main Body
            terial as well as the production of drawings with a   and two “double boogie” Floating Shoes (to over-
            “map” for the accurate placement of mats onto the   come possible gaps and misalignment) in such a
            ground. This was done just for the correct and safe   way the shoes can negotiated track crown +/‐ 2°.
            positioning of the heavy lift crawler crane.  The floating shoes are provided with stainless ste-
                                                      el at the bottom and they can slide onto the skid
            Once the vessel was on vertical position, Fagioli   tracks, which are provided with teflon pads. Fagioli
            disconnected the reactor from the tailing frame sy-  developed a skid system with skid shoes capaci-
            stem and lowered it onto temporary supports. This   ty of 1000 ton each with the possibility to couple
            operation allowed the installation of  No. 4 ‘sup-  2 skid shoes for a total of 2000 ton capacity. The
            port shelves’ at the bottom of the reactor. These   skid shoe is composed by two sections, hinged   Pict .07
            support shelves had the main function to be used   together and equipped
            as “connectors” for the skidding system which was   with n.° 2 push – pull
            subsequently used for the skidding operation.  units (composed of two
            After the installation of the support shelves (with a   jacks hydraulically linked
            weight of about 1.8 ton each) and the retaining pla-  and one anchor block),
            tes inside the “skirt” of the vessel, the reactor was   with the upper frame free
            lifted, rotated and moved by crawler crane over the   to slide transversally with
            existing pipe rack (pict.05).             respect to the skid base
                                                      +/- 50mm. A sophistica-
            The pipe rack, containing methane and cables,   ted control system provi-
            was impossible to be removed and prevented the   des high standard of syn-
            passage of the reactor by trailers or SPMTs.  chronization among the
                                                      skid shoes both for lifting
                                                      and skidding operations.
            Skidding operation                        The positioning of the re-
                                                      actor onto the skid shoes
            and final installation                    was gradually executed
                                                      with load releasing sta-
            In the meantime Fagioli operators had been prepa-  ges in steps of 20% at a
            ring a tailor made squared support frame provided   time until each skid sho-
            with clamps (pict. 06). The frame was planned, cre-  es took about 130 ton of
            ated and manufactured by Fagioli with the scope of   load (pict. 07).
            receiving the reactor in vertical position. The squa-  After checking that the
            red support frame was fixed onto No. 4 x 1,000   support frame was cor-
            ton capacity each skid shoes positioned onto skid   rectly positioned onto the