Main cost / benefit guidelines helping Customers select the tests
Pasquale Bove
Technical Authority & Machinery Knowledge Owner, Eni SpA
ANIMP and the Italian chapter of
the Society of Petroleum Engineers
have recently started collaborating
in numerous areas. One of them is
the exchange in interesting technical
publications. We are therefore very
pleased to publish here a paper by Mr.
Pasquale Bove, which will also appear
in SPE’s Quarterly Bulletin.
D. B.
In the design and construction of a oil & gas plant of the basic criteria to decide which tests have to
the main rotating machinery (turbo-alternators, be performed at the Manufacturer factory and
turbocompressors etc.) keep a key role in which at field after the package is installed and
the production. Any package, for example a connected to the plant.
“turbocompressor train” after the fabrication The concepts and criteria highlighted below are
and assembly at the Manufacturer’s factory, guidelines; variations and customization depend
need to be inspected and tested before shipment of course on the test facilities available at the
to the field. We are talking about the Performance Manufacturer’s factory.
Tests, that make final acceptance by Client’s side. For the sake of simplicity we will focus on a
The execution of the test is not mandatory; the purpose centrifugal turbocompressor train, driven by a gas
of the tests is to check the functionality of the package, turbine. For this type of package, mainly two types
according to the requirements of the technical of tests can be performed: thermodynamic tests
specification and the guaranteed performance.The and mechanical tests, along with electrical and
Performance Test will be as useful as it better simulates auxialiaries tests.
the real operating conditions of the train installed in the A list of the tests that the Manufacturer can
field and connected to the plant. perform in the factory in the presence of the
customer is presented. Each of these tests
1. When is it advisable have their own prerogatives and purposes. The
to test a package at the preliminary functionality tests are performed
Manufacturer’s factory or at internally by the Manufacturer, and usually not
field? witnessed by the Client:
• preparation and visual checks;
The main tests are described with a brief explanation • rotor balancing test;
• vibration measurements;
• leak test;
Impiantistica Italiana - Luglio-Agosto 2015 39