Page 45 - 38
P. 45

Fig. 4 - Typical closed loop

                              2. Critical factors deciding the                        that the train is ready to be installed and to start
                              testing strategy in the factory                         production.
                              or in the field
                                                                                      If during the test at factory some operational or
                                                                                      construction problems occur, the Manufaturer has
                                                                                      here the best equipment, resources and personnel

                                                                                      to correctly identify the problems and corrective

                              The Complete unit test can be performed both at actions and fix the problems before the package

                              the factory, both at field.                             is shipped.

                              In the purchase order of a compression train, the At field the situation is quite different. The

                              Client will detail which tests will have to be provided possibilities to fix the package are necessarily

                              in factory and which at field. The need of the Client, limited, particularly in locations where an after-sale

                              as final user, is of course                                               service and specialized

                              to make himself sure         The big question is the following: does      personnel are not
                              that the compressor          the execution of the complete unit test      available. If a problem
                              train fully complies         at factory bring real benefits in terms of   occur, the possibility of
                              with the operational                                                      a quick solution can be
                              requirements, at the                   schedule and cost?                 lower than at factory
                              same time optimizing The answer is a balance among time, and the time required
                              costs and schedule.          cost and operational risk. If the test is    unpredictably longer; in
                              Depending on the train       performed at factory, you will inevitably    such an occurrence the
                              complexity, a selection of                                                start of the plant is at risk.
                              the appropriate test to be        pay additional money for this.          This becomes more likely

                              performed is needed.                                                      in harsh environment, for

                              The Mechanical Runing Test is required by the API example on a offshore platform in an arctic region.

                              standards and is performed at factory only, but is As a guideline, the Complete unit test in closed

                              not sufficient for demonstrating the performance of loop at factory is recommended for the following

                              the complete train.                                     types of trains:

                              The Complete unit test and Performance Test •	 complex compressor train, i.e train with

                              at factory is also an option, even if it involves a     two or three compressor bodies plus the

                              significant impact in terms of cost.                    driver (solutions “on-line”, as shown in the

                              The big question is the following: does the             figure 5, consisting of the turbine coupling

                              execution of the complete unit test at factory bring    + mechanical gearbox + compressor bodies,

                              real benefits in terms of schedule and cost?            with considerable length of the shaftline). Such

                              The answer is a balance among time, cost and            machines do require precise alignment of the

                              operational risk. If the test is performed at factory,  rotating components and proper baseplate

                              you will inevitably pay additional money for this.      stiffness to ensure vibration levels inside the

                              On the other hand, after the test has been              limits. Figure 5 shows an example of a on-line

                              successfully performed, you will be reasonably sure     compressor train, normally used for gas re-

                                                                                      Impiantistica Italiana - Luglio-Agosto 2015 43
   40   41   42   43   44   45   46   47   48   49   50