Page 45 - 38
P. 45
Fig. 4 - Typical closed loop
2. Critical factors deciding the that the train is ready to be installed and to start
testing strategy in the factory production.
or in the field
If during the test at factory some operational or
construction problems occur, the Manufaturer has
here the best equipment, resources and personnel
to correctly identify the problems and corrective
The Complete unit test can be performed both at actions and fix the problems before the package
the factory, both at field. is shipped.
In the purchase order of a compression train, the At field the situation is quite different. The
Client will detail which tests will have to be provided possibilities to fix the package are necessarily
in factory and which at field. The need of the Client, limited, particularly in locations where an after-sale
as final user, is of course service and specialized
to make himself sure The big question is the following: does personnel are not
that the compressor the execution of the complete unit test available. If a problem
train fully complies at factory bring real benefits in terms of occur, the possibility of
with the operational a quick solution can be
requirements, at the schedule and cost? lower than at factory
same time optimizing The answer is a balance among time, and the time required
costs and schedule. cost and operational risk. If the test is unpredictably longer; in
Depending on the train performed at factory, you will inevitably such an occurrence the
complexity, a selection of start of the plant is at risk.
the appropriate test to be pay additional money for this. This becomes more likely
performed is needed. in harsh environment, for
The Mechanical Runing Test is required by the API example on a offshore platform in an arctic region.
standards and is performed at factory only, but is As a guideline, the Complete unit test in closed
not sufficient for demonstrating the performance of loop at factory is recommended for the following
the complete train. types of trains:
The Complete unit test and Performance Test • complex compressor train, i.e train with
at factory is also an option, even if it involves a two or three compressor bodies plus the
significant impact in terms of cost. driver (solutions “on-line”, as shown in the
The big question is the following: does the figure 5, consisting of the turbine coupling
execution of the complete unit test at factory bring + mechanical gearbox + compressor bodies,
real benefits in terms of schedule and cost? with considerable length of the shaftline). Such
The answer is a balance among time, cost and machines do require precise alignment of the
operational risk. If the test is performed at factory, rotating components and proper baseplate
you will inevitably pay additional money for this. stiffness to ensure vibration levels inside the
On the other hand, after the test has been limits. Figure 5 shows an example of a on-line
successfully performed, you will be reasonably sure compressor train, normally used for gas re-
Impiantistica Italiana - Luglio-Agosto 2015 43